Two-agent singe-machine scheduling with release times to minimize the total weighted completion time

被引:39
作者
Cheng, T. C. E. [2 ]
Chung, Yu-Hsiang [3 ]
Liao, Shan-Ci [1 ]
Lee, Wen-Chiung [1 ]
机构
[1] Feng Chia Univ, Dept Stat, Taichung 40724, Taiwan
[2] Hong Kong Polytech Univ, Dept Logist & Maritime Studies, Kowloon, Hong Kong, Peoples R China
[3] Natl Chiao Tung Univ, Dept Ind & Engn Management, Hsinchu, Taiwan
关键词
Scheduling; Total weighted completion time; Maximum lateness; Two agents; DATES; ALGORITHM;
D O I
10.1016/j.cor.2012.07.013
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
In many management situations multiple agents pursuing different objectives compete on the usage of common processing resources. In this paper we study a two-agent single-machine scheduling problem with release times where the objective is to minimize the total weighted completion time of the jobs of one agent with the constraint that the maximum lateness of the jobs of the other agent does not exceed a given limit. We propose a branch-and-bound algorithm to solve the problem, and a primary and a secondary simulated annealing algorithm to find near-optimal solutions. We conduct computational experiments to test the effectiveness of the algorithms. The computational results show that the branch-and-bound algorithm can solve most of the problem instances with up to 24 jobs in a reasonable amount of time and the primary simulated annealing algorithm performs well with an average percentage error of less than 0.5% for all the tested cases. (C) 2012 Elsevier Ltd. All rights reserved.
引用
收藏
页码:353 / 361
页数:9
相关论文
共 29 条
[1]   Scheduling problems with two competing agents [J].
Agnetis, A ;
Mirchandani, PB ;
Pacciarelli, D ;
Pacifici, A .
OPERATIONS RESEARCH, 2004, 52 (02) :229-242
[2]   Multi-agent single machine scheduling [J].
Agnetis, Alessandro ;
Pacciarelli, Dario ;
Pacifici, Andrea .
ANNALS OF OPERATIONS RESEARCH, 2007, 150 (01) :3-15
[3]   A Lagrangian approach to single-machine scheduling problems with two competing agents [J].
Agnetis, Alessandro ;
de Pascale, Gianluca ;
Pacciarelli, Dario .
JOURNAL OF SCHEDULING, 2009, 12 (04) :401-415
[4]   A multiple-criterion model for machine scheduling [J].
Baker, KR ;
Smith, JC .
JOURNAL OF SCHEDULING, 2003, 6 (01) :7-16
[5]   SCHEDULING WITH RELEASE DATES ON A SINGLE-MACHINE TO MINIMIZE TOTAL WEIGHTED COMPLETION-TIME [J].
BELOUADAH, H ;
POSNER, ME ;
POTTS, CN .
DISCRETE APPLIED MATHEMATICS, 1992, 36 (03) :213-231
[6]   ANNEALING METHOD FOR PCB ASSEMBLY SCHEDULING ON 2 SEQUENTIAL-MACHINES [J].
BENARIEH, D ;
MAIMON, O .
INTERNATIONAL JOURNAL OF COMPUTER INTEGRATED MANUFACTURING, 1992, 5 (06) :361-367
[7]   Multi-agent scheduling on a single machine with max-form criteria [J].
Cheng, T. C. E. ;
Ng, C. T. ;
Yuan, J. J. .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2008, 188 (02) :603-609
[8]   Multi-agent scheduling on a single machine to minimize total weighted number of tardy jobs [J].
Cheng, T. C. E. ;
Ng, C. T. ;
Yuan, J. J. .
THEORETICAL COMPUTER SCIENCE, 2006, 362 (1-3) :273-281
[9]  
CHU CB, 1992, NAV RES LOG, V39, P859, DOI 10.1002/1520-6750(199210)39:6<859::AID-NAV3220390610>3.0.CO
[10]  
2-W