Minimising earliness and tardiness by integrating production scheduling with shipping information

被引:23
作者
Ma, H. L. [1 ]
Chan, Felix T. S. [1 ]
Chung, S. H. [1 ]
机构
[1] Hong Kong Polytech Univ, Dept Ind & Syst Engn, Hong Kong, Hong Kong, Peoples R China
关键词
production planning; due date scheduling; distribution; genetic algorithm; COMMON DUE-DATE; SINGLE-MACHINE; DELIVERY; TRANSPORTATION; PENALTIES; ASSIGNMENT; NUMBER; COSTS; JOBS;
D O I
10.1080/00207543.2012.718452
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Minimisation of earliness and tardiness is known to be critical to manufacturing companies because it may induce numerous tangible and intangible problems, i.e. extra storage cost, spacing, risk of damages, penalty, etc. In literature, earliness and tardiness is usually determined based on order due date, generally regarded as the time of delivering the finished products to the customers. In many papers, delivery time and cost required are usually simplified during the production scheduling. They usually assume that transportation is always available and unlimited. However, transportation usually constructs a critical portion of the total lead time and total cost in practice. Ignoring that will lead to an unreliable schedule. This is especially significant for electronic household appliances manufacturing companies as the studied company in this paper. In general, they usually rely on sea-freight transportation because of the economic reasons. As different sea-freight forwarders have different shipments to the same destination but with different shipping lead time, cost and available time. Adequately considering this shipping information with the production scheduling as an integrated model can minimise the costs induced by earliness and tardiness and the reliability of the schedule planned. In this paper, a two-level genetic algorithm (TLGA) is proposed, which is capable of simultaneously determining production schedule with shipping information. The optimisation reliability of the proposed TLGA is tested by comparing with a simple genetic algorithm. The results indicated that the proposed TLGA can obtain a better solution with lesser number of evolutions. In addition, a number of numerical experiments are carried out. The results demonstrate that the proposed integrated approach can reduce the tardiness, the storage cost, and shipping cost.
引用
收藏
页码:2253 / 2267
页数:15
相关论文
共 31 条
[1]  
[Anonymous], 1975, Ann Arbor
[2]   Development of a hybrid metaheuristic to minimise earliness and tardiness in a hybrid flowshop with sequence-dependent setup times [J].
Behnamian, J. ;
Ghomi, S. M. T. Fatemi ;
Zandieh, M. .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2010, 48 (05) :1415-1438
[3]   Multicriterion genetic optimization for due date assigned distribution network problems [J].
Chan, FTS ;
Chung, SH .
DECISION SUPPORT SYSTEMS, 2005, 39 (04) :661-675
[4]   Machine scheduling with job delivery coordination [J].
Chang, YC ;
Lee, CY .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2004, 158 (02) :470-487
[5]   Order assignment and scheduling in a supply chain [J].
Chen, ZL ;
Pundoor, G .
OPERATIONS RESEARCH, 2006, 54 (03) :555-572
[6]   Integrated scheduling of production and distribution operations [J].
Chen, ZL ;
Vairaktarakis, GL .
MANAGEMENT SCIENCE, 2005, 51 (04) :614-628
[7]   Scheduling and common due date assignment with earliness-tardiness penalties and batch delivery costs [J].
Chen, ZL .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1996, 93 (01) :49-60
[8]  
CHENG TCE, 1993, ASIA PAC J OPER RES, V10, P145
[9]   Single machine scheduling with batch deliveries [J].
Cheng, TCE ;
Gordon, VS ;
Kovalyov, MY .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1996, 94 (02) :277-283
[10]   Minimization of Order Tardiness Through Collaboration Strategy in Multifactory Production System [J].
Chung, S. H. ;
Chan, Felix T. S. ;
Ip, Wai Hung .
IEEE SYSTEMS JOURNAL, 2011, 5 (01) :40-49