Model and scheduling of a continuous galvanizing line

被引:0
作者
Gao, Cong [1 ]
Tang, Lixin [1 ]
Wang, Ying [1 ]
机构
[1] Northeastern Univ, Inst Logist, Shenyang, Liaoning, Peoples R China
来源
IEEE/SOLI'2008: PROCEEDINGS OF 2008 IEEE INTERNATIONAL CONFERENCE ON SERVICE OPERATIONS AND LOGISTICS, AND INFORMATICS, VOLS 1 AND 2 | 2008年
关键词
Tabu Search; steel industry; modeling;
D O I
10.1109/SOLI.2008.4682827
中图分类号
TM [电工技术]; TN [电子技术、通信技术];
学科分类号
0808 ; 0809 ;
摘要
In this paper, we introduce a continuous galvanizing line in a steel plant which is one of the biggest iron and steel enterprises of the world. The continuous galvanizing line we research produces principally two kinds of coils, inner coils and outer coils. Due to the technical constraint, outer coils can not be produced continuously more than a specified number. So the inner coils must be inserted between outer coils. The difficulty of solving the problem is the interrelation of sequencing these two kinds of coils. No model and algorithm about such a scheduling problem has. been published. We propose an integer programming model to describe the scheduling problem. To solve the problem, a heuristic based on tabu search is developed. Due to the model of the scheduling problem is an integer programming model, problems with less than 100 coils can be solved by CPLEX 11.0 MIP optimizer to obtain the optimal solution or a lower bound of the problem. By comparing our heuristic schedule and the CPLEX schedule, the tabu search heuristic is proven to be effective.
引用
收藏
页码:1829 / 1834
页数:6
相关论文
共 50 条
  • [31] An MILP Model for the Internal Audit Scheduling Problem
    Yildirim, V.
    Angun, M. E.
    Oncan, T.
    2018 IEEE INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND ENGINEERING MANAGEMENT (IEEE IEEM), 2018, : 442 - 446
  • [32] A general model for cyclic machine scheduling problems
    Brucker, Peter
    Kampmeyer, Thomas
    DISCRETE APPLIED MATHEMATICS, 2008, 156 (13) : 2561 - 2572
  • [33] Heuristic approaches to discrete-continuous project scheduling problems to minimize the makespan
    Waligora, Grzegorz
    COMPUTATIONAL OPTIMIZATION AND APPLICATIONS, 2011, 48 (02) : 399 - 421
  • [34] A continuous growth model for plant tissue
    Bozorg, Behruz
    Krupinski, Pawel
    Jonsson, Henrik
    PHYSICAL BIOLOGY, 2016, 13 (06)
  • [35] Genetic Algorithm for a Discrete-Continuous Project Scheduling Problem with Discounted Cash Flows
    Waligora, Grzegorz
    2015 20TH INTERNATIONAL CONFERENCE ON METHODS AND MODELS IN AUTOMATION AND ROBOTICS (MMAR), 2015, : 52 - 57
  • [36] Optimization Model for Capacity Management and Bed Scheduling for Hospital
    Sitepu, Suryati
    Mawengkang, Herman
    Husein, Ismail
    4TH INTERNATIONAL CONFERENCE ON OPERATIONAL RESEARCH (INTERIOR), 2018, 300
  • [37] Development and testing of a GIS integrated irrigation scheduling model
    George, BA
    Raghuwanshi, NS
    Singh, R
    AGRICULTURAL WATER MANAGEMENT, 2004, 66 (03) : 221 - 237
  • [38] Real-time irrigation scheduling model for cotton
    Li, YH
    Dong, B
    WATER AND THE ENVIRONMENT: INNOVATIVE ISSUES IN IRRIGATION AND DRAINAGE, 1998, : 197 - 204
  • [39] Discrete-continuous project scheduling with discounted cash flows -: A tabu search approach
    Waligora, Grzegorz
    COMPUTERS & OPERATIONS RESEARCH, 2008, 35 (07) : 2141 - 2153
  • [40] Train Routing Model and Algorithm Combined with Train Scheduling
    Li, Feng
    Gao, Ziyou
    Li, Keping
    Wang, David Z. W.
    JOURNAL OF TRANSPORTATION ENGINEERING-ASCE, 2013, 139 (01): : 81 - 91