Key Chain Buffer Setting Method for Uncertainty of Project Duration

被引:0
作者
Zhang, Fenglin [1 ]
Gao, Xingming [1 ]
机构
[1] Nanjing Univ Aeronaut & Astronaut, Coll Econ & Management, 29 Jiangjun St, Nanjing 211106, Jiangsu, Peoples R China
来源
MAN-MACHINE-ENVIRONMENT SYSTEM ENGINEERING, MMESE 2018 | 2019年 / 527卷
关键词
Progress analysis; Entropy weight method; Buffer; Uncertainty;
D O I
10.1007/978-981-13-2481-9_69
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
Project duration uncertainty has become a problem of project progress analysis. In particular, the duration of some project processes is in a very large range. In order to solve this problem, this article measures the uncertainty coefficient of the process based on the entropy method and calculates the definite duration of the project process. Then, this article introduces the project risk coefficient red line, based on the relative risk coefficient to establish the key chain buffer and non-key chain buffer setting model, setting the project buffer to calculate its duration. Combined with the example and compared with the shear-paste method, it proves that this method is more scientific, reasonable, and effective.
引用
收藏
页码:593 / 599
页数:7
相关论文
共 5 条
[1]  
Chen H, 2015, J SYST ADMIN, V24, P237
[2]  
Peng W, 2013, J SYST MANAG, V22, P855
[3]  
Xu X, 2007, IND ENG MANAG, V05, P51
[4]  
Zhang Jing-wen, 2013, Control and Decision, V28, P1281
[5]  
Zhang Min, 2009, Industrial Engineering and Management, V14, P54