A mixed integer linear programming model for unit commitment of thermal plants with peak shaving operation aspect in regional power grid lack of flexible hydropower energy

被引:110
作者
Feng, Zhong-kai [1 ]
Niu, Wen-jing [2 ]
Wang, Wen-chuan [3 ]
Zhou, Jian-zhong [1 ]
Cheng, Chun-tian [4 ]
机构
[1] Huazhong Univ Sci & Technol, Sch Hydropower & Informat Engn, Wuhan 430074, Hubei, Peoples R China
[2] Changjiang Water Resources Commiss, Bur Hydrol, Wuhan 430010, Hubei, Peoples R China
[3] North China Univ Water Resources & Elect Power, Sch Water Conservancy, Zhengzhou 450046, Henan, Peoples R China
[4] Dalian Univ Technol, Inst Hydropower & Hydroinformat, Dalian 116024, Peoples R China
基金
中国国家自然科学基金;
关键词
Mixed integer linear programming (MILP); Thermal power plants; Unit commitment; Peak shaving operation; Regional power grid; CULTURAL DIFFERENTIAL EVOLUTION; SCALE PHOTOVOLTAIC POWER; SYSTEM OPERATION; ECONOMIC EMISSION; WIND POWER; OPTIMIZATION; UNCERTAINTY; RESERVOIR; GENERATION; MANAGEMENT;
D O I
10.1016/j.energy.2019.03.117
中图分类号
O414.1 [热力学];
学科分类号
摘要
Recently, the booming electricity demand and intermittent energy has sharply increased the peak shaving pressure in China. However, for a majority of regional power grids in China, the installed capacity of flexible energy (like hydropower and pumped-storage) is small and the thermal plants are asked to respond the sudden load change at peak periods. The existing method based on specialist experience and historical information may generate inferior solutions and fail to reduce the peak pressure. Thus, a practical mixed integer linear programming (MILP) model is developed for unit commitment of thermal plants with peak shaving operation aspect in regional power grid lack of flexible hydropower energy, where the goal is chosen to minimize the peak-valley difference of the residual load series obtained by subtracting all the thermal generation from the original load curve while satisfying the necessary physical constraints. The MILP model is used to the thermal system in the China's largest regional power grid, East China Power Grid. The simulations show that the MILP model can effectively smooth the residual load curve by gathering power generation of thermal plants at peak periods. Therefore, an alternative tool is provided to alleviate the peak pressure of thermal-dominant regional power grid in China. (C) 2019 Elsevier Ltd. All rights reserved.
引用
收藏
页码:618 / 629
页数:12
相关论文
共 50 条
[1]  
[Anonymous], WATER RESOURCES RES
[2]   Maximizing hydro share in peak demand of power systems long-term operation planning [J].
Brandi, Rafael Bruno S. ;
Ramos, Tales Pulinho ;
David, Pedro A. M. -S. ;
Dias, Bruno Henriques ;
da Silva Junior, Ivo Chaves ;
Marques Marcato, Andre Luis .
ELECTRIC POWER SYSTEMS RESEARCH, 2016, 141 :264-271
[3]   Solving nonlinear water management models using a combined genetic algorithm and linear programming approach [J].
Cai, XM ;
McKinney, DC ;
Lasdon, LS .
ADVANCES IN WATER RESOURCES, 2001, 24 (06) :667-676
[4]   Optimal hydro scheduling and offering strategies considering price uncertainty and risk management [J].
Catalao, J. P. S. ;
Pousinho, H. M. I. ;
Contreras, J. .
ENERGY, 2012, 37 (01) :237-244
[5]   Hydro energy systems management in Portugal: Profit-based evaluation of a mixed-integer nonlinear approach [J].
Catalao, J. P. S. ;
Pousinho, H. M. I. ;
Mendes, V. M. F. .
ENERGY, 2011, 36 (01) :500-507
[6]   Scheduling of head-dependent cascaded reservoirs considering discharge ramping constraints and start/stop of units [J].
Catalao, J. P. S. ;
Pousinho, H. M. I. ;
Mendes, V. M. F. .
INTERNATIONAL JOURNAL OF ELECTRICAL POWER & ENERGY SYSTEMS, 2010, 32 (08) :904-910
[7]   A practical approach for profit-based unit commitment with emission limitations [J].
Catalao, J. P. S. ;
Mariano, S. J. P. S. ;
Mendes, V. M. F. ;
Ferreira, L. A. F. M. .
INTERNATIONAL JOURNAL OF ELECTRICAL POWER & ENERGY SYSTEMS, 2010, 32 (03) :218-224
[8]   Parameterisation effect on the behaviour of a head-dependent hydro chain using a nonlinear model [J].
Catalao, JPS ;
Mariano, SJPS ;
Mendes, VMF ;
Ferreira, LAFM .
ELECTRIC POWER SYSTEMS RESEARCH, 2006, 76 (6-7) :404-412
[9]   Modeling, nonlinear dynamical analysis of a novel power system with random wind power and it's control [J].
Chen, Diyi ;
Liu, Si ;
Ma, Xiaoyi .
ENERGY, 2013, 53 :139-146
[10]   An inexact optimization modeling approach for supporting energy systems planning and air pollution mitigation in Beijing city [J].
Dong, C. ;
Huang, G. H. ;
Cai, Y. P. ;
Liu, Y. .
ENERGY, 2012, 37 (01) :673-688