Evaluation of the effect of compaction on the behavior of geosynthetic-reinforced soil walls

被引:94
作者
Ehrlich, M. [1 ]
Mirmoradi, S. H. [1 ]
Saramago, R. P. [2 ]
机构
[1] Univ Fed Rio de Janeiro, Dept Civil Engn, COPPE, BR-21945970 Rio De Janeiro, RJ, Brazil
[2] Univ Fed Fluminense, Dept Civil Engn, BR-24210240 Niteroi, RJ, Brazil
关键词
Physical modeling; Geosynthetic; Reinforced soil; Walls; Compaction effort; STRESS DESIGN METHOD; K-STIFFNESS METHOD; SEGMENTAL RETAINING WALLS; FINITE-ELEMENT; PERFORMANCE; LOADS;
D O I
10.1016/j.geotexmem.2012.05.005
中图分类号
P5 [地质学];
学科分类号
0709 ; 081803 ;
摘要
This paper presents a physical model study of the influence of compaction on the behavior of geogrid-reinforced soil walls. Experiments were accomplished in a facility at the Geotechnical Laboratory of COPPE/UFRJ. For soil compaction, two different types of hand-operated compactors were used: a vibrating plate and a vibratory tamper. Equivalent vertical stresses for the vibrating plate (referred to as the "light compactor") were much lower than the corresponding value of the vibratory tamper (referred to as the "heavy compactor"). Mobilized tension along the reinforcements and external and internal displacements of the wall were monitored. The results showed that the effect of soil compaction is not limited to a reduction of the soil void ratio. Compaction has led to a significant increase in the horizontal stress inside the reinforced soil mass and generates a kind of pre-consolidated material. Analyses of results showed that compaction has played a decisive factor in terms of the reinforcement tensions and post-construction displacements. The connection load was much less in a wall with heavy compaction than that in a wall with light compaction. Results also showed that the position of maximum tensile force mobilized in the reinforcements was nearer to the face in the wall with heavy compaction. On the other hand, the mobilized tension measured along the reinforcement layers at the end of construction in the wall where heavy soil compaction was used was much higher than the values of tension measured in the wall where light soil compaction was applied. Nevertheless, it was observed that the difference in the mobilized tensions in the reinforcements of these two walls decreased with increase in the value of the external surcharge load. (C) 2012 Elsevier Ltd. All rights reserved.
引用
收藏
页码:108 / 115
页数:8
相关论文
共 37 条
[1]   New procedure for active earth pressure calculation in retaining walls with reinforced cohesive-frictional backfill [J].
Ahmadabadi, M. ;
Ghanbari, A. .
GEOTEXTILES AND GEOMEMBRANES, 2009, 27 (06) :456-463
[2]   A new working stress method for prediction of reinforcement loads in geosynthetic walls [J].
Allen, TM ;
Bathurst, RJ ;
Holtz, RD ;
Walters, D ;
Lee, WF .
CANADIAN GEOTECHNICAL JOURNAL, 2003, 40 (05) :976-994
[3]   Global level of safety and performance of geosynthetic walls: An historical perspective [J].
Allen, TM ;
Bathurst, RJ ;
Berg, RR .
GEOSYNTHETICS INTERNATIONAL, 2002, 9 (5-6) :395-450
[4]  
[Anonymous], 2002, Standard Specifications for Highway Bridges
[5]  
[Anonymous], 1996, Standard specifications for highway bridges
[6]  
Barboza Junior J. C., 2003, THESIS UFRJ RIO DE J
[7]   Refinement of K-stiffness Method for geosynthetic-reinforced soil walls [J].
Bathurst, R. J. ;
Miyata, Y. ;
Nernheim, A. ;
Allen, A. M. .
GEOSYNTHETICS INTERNATIONAL, 2008, 15 (04) :269-295
[8]   Influence of reinforcement stiffness and compaction on the performance of four geosynthetic-reinforced soil walls [J].
Bathurst, R. J. ;
Nernheim, A. ;
Walters, D. L. ;
Allen, T. M. ;
Burgess, P. ;
Saunders, D. D. .
GEOSYNTHETICS INTERNATIONAL, 2009, 16 (01) :43-59
[9]   Reinforcement loads in geosynthetic walls and the case for a new working stress design method [J].
Bathurst, RJ ;
Allen, TM ;
Walters, DL .
GEOTEXTILES AND GEOMEMBRANES, 2005, 23 (04) :287-322
[10]   Field monitoring evaluation of geotextile-reinforced soil-retaining walls [J].
Benjamim, C. V. S. ;
Bueno, B. S. ;
Zornberg, J. G. .
GEOSYNTHETICS INTERNATIONAL, 2007, 14 (02) :100-118