Automated process planning system: A new method for setup planning and a mathematical model for fixture design

被引:10
|
作者
Abedini, Vahid [1 ]
Shakeri, Mohsen [1 ]
Siahmargouei, Mohammad Hasan [1 ]
Baseri, Hamid [1 ]
机构
[1] Babol Noshirvani Univ Technol, Fac Mech Engn, Babol Sar 471487116, Mazandaran, Iran
关键词
Setup planning; fixture design; prismatic components; position tolerance; hole making; GRAPH APPROACH; OPTIMIZATION; CAPP;
D O I
10.1177/0954405413492731
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Setup planning and fixture design are two main tasks for the integration of design and manufacturing process. Setup planning identifies which features must be machined in each setup and determines locating datum for each setup, whereas fixture planning determines precise locating and rigid clamping of workpieces according to a part design and process requirements. So, a close interaction exists between setup planning and fixture design. This research deals with the problems of setup and fixture planning for the machining of prismatic parts. In the first step, a new heuristic method is presented to plan the setups with accurate respect to datum faces in design and manufacturing. Two concepts, namely, inferiority face and control face, have been used for this purpose. In the next step, a mathematical model is used to define the primary, secondary and tertiary fixture planes with respect to locators' position. This model determines relationship between misplacement of locators and dimensional and geometrical specifications of workpiece. The main purpose of developing the model is to determine the effect of locator height error on hole position tolerance. The capability of this model is verified by simulation in motion study module in SolidWorks software. This approach is very useful in the hole-making process. The system is developed in Visual Basic on a SolidWorks platform. The effectiveness of the system is verified by an industrial component.
引用
收藏
页码:1849 / 1859
页数:11
相关论文
共 50 条
  • [31] Automated modular fixture planning: Geometric analysis
    Wu, Y
    Rong, Y
    Ma, W
    LeClair, SR
    ROBOTICS AND COMPUTER-INTEGRATED MANUFACTURING, 1998, 14 (01) : 1 - 15
  • [32] Geometric theory on automated modular fixture planning
    Wu, Yuguang
    Gao, Shuming
    Chen, Zichen
    Jixie Gongcheng Xuebao/Chinese Journal of Mechanical Engineering, 2002, 38 (01): : 117 - 122
  • [33] Project model for an automated building system: Design and planning phases
    Sacks, Rafael
    Warszawski, Abraham
    Automation in construction, 1997, 7 (01): : 21 - 34
  • [34] A new directed graph approach for automated setup planning in CAPP
    Sun, Xiwu
    Chu, Xuening
    Su, Yuliang
    Tang, Censhu
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2010, 48 (22) : 6583 - 6612
  • [35] Automated setup planning for lathe machining
    Huang, SH
    JOURNAL OF MANUFACTURING SYSTEMS, 1998, 17 (03) : 196 - 208
  • [36] EXPERIMENT PLANNING METHOD IN SEEKING THE FRICTION PROCESS MATHEMATICAL MODEL.
    Gekker, F.R.
    Rybalkin, A.G.
    Soviet Journal of Friction and Wear (English translation of Trenie i Iznos), 1984, 5 (01): : 77 - 82
  • [37] An integrated setup/fixture planning approach for machining prismatic parts
    Sun, Xiwu
    Chu, Xuening
    Xue, Deyi
    Su, Yuliang
    Tang, Censhu
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2012, 50 (04) : 1009 - 1027
  • [38] Operational dimensioning and tolerancing in process planning: Setup planning
    Zhang, HC
    Huang, SH
    Mei, J
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1996, 34 (07) : 1841 - 1858
  • [39] A flexible mathematical model for the planning and designing of a sporting fixture by considering the assignment of referees
    Linfati, Rodrigo
    Gatica, Gustavo
    Willmer Escobar, John
    INTERNATIONAL JOURNAL OF INDUSTRIAL ENGINEERING COMPUTATIONS, 2019, 10 (02) : 281 - 294
  • [40] A Fixture Assembly Process Planning Method Based on a Particle Swarm Algorithm
    Cao, Yan
    Wu, Yujia
    Cao, Sen
    PROCEEDINGS OF THE 2015 INTERNATIONAL INDUSTRIAL INFORMATICS AND COMPUTER ENGINEERING CONFERENCE, 2015, : 563 - 566