摘要
This paper presents the accelerated operation scheme of the adaptive noncommunication protection technique for power lines with complex configurations, such as multi-end feeder and ring main. In the scheme, the overcurrent directional relays are arranged in two operating modes, the fixed time operation and accelerated operation. The relays with faster operating time in the conventional time grading coordination remain unchanged. The new technique is employed to enable accelerated operation to be achieved for the relays which are in the positions for which slow operating time is set when using conventional time grading technique. For a fault occurring on the protected system, the relays of fixed time operation mode will operate at the preset time for the fault within its protected direction. The relays which are programmed to use accelerated operation mode will determine whether a fault is on the protected section or not by using the BO technique, that is to detect the circuit breaker operation by determining whether the line section is in a balanced operation condition or not. The relay makes accelerated tripping decisions for a fault on its protected section. Simulation studies of the responses to various system and fault conditions show that the scheme can significantly increase the speed of the relay responses in the protection of power line systems with complex configurations.
引用
收藏
页码:97 / 104
页数:8
相关论文
共 3 条
[1]   Adaptive non-communication protection for power lines BO scheme 2 - The instant operation approach [J].
Bo, ZQQ .
IEEE TRANSACTIONS ON POWER DELIVERY, 2002, 17 (01) :92-96
[2]   Adaptive non-communication protection for power lines BO scheme 1 - The delayed operation approach [J].
Bo, ZQQ .
IEEE TRANSACTIONS ON POWER DELIVERY, 2002, 17 (01) :85-91
[3]  
*GEC ALSTH T D PRO, 1990, PROT REL APPL GUID