Robust flow shop scheduling with random processing times for reduction of peak power consumption

被引:21
作者
Nagasawa, Keisuke [1 ]
Ikeda, Yuto [2 ]
Irohara, Takashi [2 ]
机构
[1] Hiroshima Univ, Div Elect Syst & Math Engn, Fac Engn, Higashihiroshima 7398527, Japan
[2] Sophia Univ, Dept Informat & Commun Sci, Chiyoda Ku, Tokyo 1028554, Japan
关键词
Flow shop scheduling; Peak power; Random processing time; Simulation; PARALLEL MACHINES; ENERGY-CONSUMPTION; SETUP TIMES; JOBS; ALGORITHM; SYSTEM;
D O I
10.1016/j.simpat.2015.08.001
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
Recently, power shortages have become a major problem all over Japan, due to the Great East Japan Earthquake, which resulted in the shutdown of a nuclear power plant. As a consequence, production scheduling has become a problem for factories, due to considerations of the availability of electric power. For factories, the contract with the electric power company sets the maximum power demand for a unit period, and in order to minimize this, it is necessary to consider the peak power when scheduling production. There are conventional studies on flowshop scheduling with consideration of peak power. However, these studies did not consider fluctuations in the processing time. Because the actual processing time is not constant, there is an increase in the probability of simultaneous operations with multiple machines. If the probability of simultaneous operations is high, the probability of increasing the peak power is high. Thus, we consider inserting idle time (delay in inputting parts) into the schedule in order to reduce the likelihood of simultaneous operations. We consider a robust schedule that limits the peak power, in spite of an unexpected fluctuation in the processing time. However, when we insert idle time, the makespan gets longer, and the production efficiency decreases. Therefore, we performed simulations to investigate the optimal amount of idle time and the best point for inserting it. We propose a more robust production scheduling model that considers random processing times and the peak power consumption. The results of experiments show that the effectiveness of the schedule produced by the proposed method is superior to the initial schedule and to a schedule produced by another method. Thus, the use of random processing times can limit the peak power. (C) 2015 Elsevier B.V. All rights reserved.
引用
收藏
页码:102 / 113
页数:12
相关论文
共 50 条
[21]   Green Hybrid Flow Shop Scheduling Problem Considering Sequence Dependent Setup Times and Transportation Times [J].
Wu, Shaoxing ;
Liu, Li .
IEEE ACCESS, 2023, 11 :39726-39737
[22]   No idle flow shop scheduling models for optimization of machine rental costs with processing and separated setup times [J].
Singla, Shakuntla ;
Kaur, Harshleen ;
Gupta, Deepak ;
Modibbo, Umar Muhammad ;
Kaur, Jatinder .
FRONTIERS IN APPLIED MATHEMATICS AND STATISTICS, 2024, 10
[23]   Heuristics for permutation flow shop scheduling with batch setup times [J].
Sotskov, YN ;
Tautenhahn, T ;
Werner, F .
OR SPEKTRUM, 1996, 18 (02) :67-80
[24]   Group Building Based Power Consumption Scheduling for the Electricity Cost Minimization with Peak Load Reduction [J].
Oh, Eunsung ;
Park, Jong-Bae ;
Son, Sung-Yong .
JOURNAL OF ELECTRICAL ENGINEERING & TECHNOLOGY, 2014, 9 (06) :1843-1850
[25]   An immune algorithm for scheduling a hybrid flow shop with sequence-dependent setup times and machines with random breakdowns [J].
Zandieh, M. ;
Gholami, M. .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2009, 47 (24) :6999-7027
[26]   Scheduling With Uncertain Processsing Times: Applying β-Robust Schedule On Two-Machine Flow-Shop With Constraints [J].
Ullah, Saif ;
Liu, Qiong ;
Zhang, Chaoyong ;
Awan, Yasser Riaz .
2009 IEEE INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND ENGINEERING MANAGEMENT, VOLS 1-4, 2009, :1946-1950
[27]   A robust simulated annealing heuristic for flow shop scheduling problems [J].
Chinyao Low ;
Jinn-Yi Yeh ;
Kai-I Huang .
The International Journal of Advanced Manufacturing Technology, 2004, 23 :762-767
[28]   A robust simulated annealing heuristic for flow shop scheduling problems [J].
Low, C ;
Yeh, JY ;
Huang, KI .
INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2004, 23 (9-10) :762-767
[29]   Robust single machine scheduling for minimizing total flow time in the presence of uncertain processing times [J].
Lu, Chung-Cheng ;
Ying, Kuo-Ching ;
Lin, Shih-Wei .
COMPUTERS & INDUSTRIAL ENGINEERING, 2014, 74 :102-110
[30]   Scheduling flexible flow shop with recirculation and machine sequence-dependent processing times: formulation and solution procedures [J].
Ahonen, Hannu ;
de Alvarenga, Arlindo Gomes .
INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2017, 89 (1-4) :765-777