Robust flow shop scheduling with random processing times for reduction of peak power consumption

被引:21
|
作者
Nagasawa, Keisuke [1 ]
Ikeda, Yuto [2 ]
Irohara, Takashi [2 ]
机构
[1] Hiroshima Univ, Div Elect Syst & Math Engn, Fac Engn, Higashihiroshima 7398527, Japan
[2] Sophia Univ, Dept Informat & Commun Sci, Chiyoda Ku, Tokyo 1028554, Japan
关键词
Flow shop scheduling; Peak power; Random processing time; Simulation; PARALLEL MACHINES; ENERGY-CONSUMPTION; SETUP TIMES; JOBS; ALGORITHM; SYSTEM;
D O I
10.1016/j.simpat.2015.08.001
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
Recently, power shortages have become a major problem all over Japan, due to the Great East Japan Earthquake, which resulted in the shutdown of a nuclear power plant. As a consequence, production scheduling has become a problem for factories, due to considerations of the availability of electric power. For factories, the contract with the electric power company sets the maximum power demand for a unit period, and in order to minimize this, it is necessary to consider the peak power when scheduling production. There are conventional studies on flowshop scheduling with consideration of peak power. However, these studies did not consider fluctuations in the processing time. Because the actual processing time is not constant, there is an increase in the probability of simultaneous operations with multiple machines. If the probability of simultaneous operations is high, the probability of increasing the peak power is high. Thus, we consider inserting idle time (delay in inputting parts) into the schedule in order to reduce the likelihood of simultaneous operations. We consider a robust schedule that limits the peak power, in spite of an unexpected fluctuation in the processing time. However, when we insert idle time, the makespan gets longer, and the production efficiency decreases. Therefore, we performed simulations to investigate the optimal amount of idle time and the best point for inserting it. We propose a more robust production scheduling model that considers random processing times and the peak power consumption. The results of experiments show that the effectiveness of the schedule produced by the proposed method is superior to the initial schedule and to a schedule produced by another method. Thus, the use of random processing times can limit the peak power. (C) 2015 Elsevier B.V. All rights reserved.
引用
收藏
页码:102 / 113
页数:12
相关论文
共 50 条
  • [1] Flow shop scheduling with peak power consumption constraints
    Kan Fang
    Nelson A. Uhan
    Fu Zhao
    John W. Sutherland
    Annals of Operations Research, 2013, 206 : 115 - 145
  • [2] Flow shop scheduling with peak power consumption constraints
    Fang, Kan
    Uhan, Nelson A.
    Zhao, Fu
    Sutherland, John W.
    ANNALS OF OPERATIONS RESEARCH, 2013, 206 (01) : 115 - 145
  • [3] Decoding methods for the flow shop scheduling with peak power consumption constraints
    Wang, Jing-jing
    Wang, Ling
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2019, 57 (10) : 3200 - 3218
  • [4] Robust Scheduling of Two-Stage Flow Shop with Interval Processing Times
    Zhang, Xianchao
    Zhou, Hong
    Computer Engineering and Applications, 2023, 59 (20) : 266 - 273
  • [5] Robust scheduling of a two-machine flow shop with uncertain processing times
    Kouvelis, P
    Daniels, RL
    Vairaktarakis, G
    IIE TRANSACTIONS, 2000, 32 (05) : 421 - 432
  • [6] Robust scheduling of a two-machine flow shop with uncertain processing times
    Kouvelis, Panos
    Daniels, Richard L.
    Vairaktarakis, George
    IIE Transactions (Institute of Industrial Engineers), 2000, 32 (05): : 421 - 432
  • [7] Flow shop scheduling with flexible processing times
    Bultmann, Matthias
    Knust, Sigrid
    Waldherr, Stefan
    OR SPECTRUM, 2018, 40 (03) : 809 - 829
  • [8] Flow shop scheduling with flexible processing times
    Matthias Bultmann
    Sigrid Knust
    Stefan Waldherr
    OR Spectrum, 2018, 40 : 809 - 829
  • [9] Considering the peak power consumption problem with learning and deterioration effect in flow shop scheduling
    Lv, Dan-Yang
    Wang, Ji-Bo
    COMPUTERS & INDUSTRIAL ENGINEERING, 2024, 197
  • [10] Robust Model for Job Shop Scheduling with Uncertain Processing Times
    Wang, Bing
    Yang, Xiaofei
    CCDC 2009: 21ST CHINESE CONTROL AND DECISION CONFERENCE, VOLS 1-6, PROCEEDINGS, 2009, : 2484 - 2489