Analysis of Deformation Characteristics of Large Diameter Shield Tunnel with Construction Load

被引:1
|
作者
Zhu, Weidong [1 ]
Zhang, Xiwen [1 ,2 ]
Zhang, Liangliang [3 ]
机构
[1] Univ Jinan, Sch Civil Engn & Architecture, Jinan, Shandong, Peoples R China
[2] Engn Technol Res Ctr Urban Underground Engn Suppo, Jinan 250022, Shandong, Peoples R China
[3] China Railway Siyuan Survey & Design Grp Co Ltd, Wuhan, Hubei, Peoples R China
关键词
Shield tunnel; Internal structure; Structure deformation; Construction load; Assembly structure;
D O I
10.1007/978-981-19-1260-3_41
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
With the rapid development of the method of shield tunnel in our country, the shield in the tunnel and the internal structure exist a lot of prefabricated and assembled internal structure can be roughly divided into full cast-in-place, full precast, and precast and cast-in-place structure. However, it has the disadvantages of more internal structural joints, poor waterproof performance, and complex structural stress. Therefore, combined with the actual engineering case, the construction process is simulated by using the finite element analysis software, and the influence of the segmental and internal structure cooperative deformation and joint mechanical performance is considered to further analyze the deformation characteristics of shield tunnel assembly internal structure, which can provide a reference for the construction and design of similar projects.
引用
收藏
页码:455 / 461
页数:7
相关论文
共 50 条
  • [31] Longitudinal deformation of Shield tunnel based on construction monitoring data
    Yao, Wenkang
    JOURNAL OF VIBROENGINEERING, 2023, 25 (05) : 964 - 980
  • [32] Dynamic response analysis of ultra-large diameter shield tunnel in uneven soft and hard strata under surface blast load
    Yang, Chunshan
    Wei, Lixin
    Zhu, Min
    Liu, Liying
    Bao, Xiaohua
    Zhao, Zeqian
    Chen, Xiangsheng
    Zhendong yu Chongji/Journal of Vibration and Shock, 2024, 43 (21): : 12 - 20
  • [33] Disaster mechanism analysis for segments floating of large-diameter shield tunnel construction in the water-rich strata: A case study
    Shi, Zhou
    Xu, Jinfeng
    Xie, Xiongyao
    Zeng, Hongbo
    Xu, Weijiang
    Niu, Gang
    Xiao, Zhonglin
    ENGINEERING FAILURE ANALYSIS, 2024, 157
  • [34] Study of key construction technique and mechanical performance of metro station constructed by enlarging large diameter shield tunnel
    Sun, Changjun
    Zhang, Dingli
    Zheng, Hao
    Wang, Le
    Tumu Gongcheng Xuebao/China Civil Engineering Journal, 2015, 48 : 293 - 296
  • [35] RESEARCH ON CONSTRUCTION TECHNOLOGY OF LARGE-DIAMETER SHIELD TUNNEL IN SHALLOW COVER SECTION OF RED STRATA GEOLOGY
    Ouyang, Jian
    Wang, Haijun
    Dong, Xin
    Hu, Dawei
    Zhang, Kexin
    Xue, Xingwei
    CIVIL ENGINEERING JOURNAL-STAVEBNI OBZOR, 2024, 33 (02): : 181 - 198
  • [36] Construction safety analysis on the process of large diameter shield traversing shallow overburden soil
    Ye Fei
    Zhu Hehua
    Ding Wenqi
    PROGRESS IN SAFETY SCIENCE AND TECHNOLOGY, VOL 6, PTS A AND B, 2006, 6 : 2177 - 2180
  • [37] Analysis of the impact of large-diameter shield construction adjacent to the side of the pile foundation
    Ma, Wenbin
    Liu, Junyan
    Zhang, Liangliang
    2020 2ND INTERNATIONAL CONFERENCE ON CIVIL ENGINEERING, ENVIRONMENT RESOURCES AND ENERGY MATERIALS, 2021, 634
  • [38] Analysis of construction interaction of highway shield tunnels with short-distance and large diameter
    Chen Jian-feng
    Wang Xin
    Shi Zhen-ming
    Chu Wei-hong
    Wang Yan-ling
    ROCK AND SOIL MECHANICS, 2010, 31 : 242 - +
  • [39] Safety analysis for metro station constructed by enlarging large diameter shield tunnel with mining method
    Li, Xiwei
    Zheng, Hao
    Wang, Quanxian
    Tumu Gongcheng Xuebao/China Civil Engineering Journal, 2016, 49 (09): : 96 - 102
  • [40] Comparative Analysis of Schemes for Metro Station Built by Enlarging Large-Diameter Shield Tunnel
    Yan, Mei
    Yang, Xiuren
    Li, Aimin
    Wang, Wenjun
    Ding, Deyun
    ADVANCES IN CIVIL ENGINEERING AND ARCHITECTURE INNOVATION, PTS 1-6, 2012, 368-373 : 2731 - +