Scheduling parallel machines with resource-dependent processing times

被引:33
|
作者
Su, Ling-Huey [1 ]
Lien, Chun-Yuan [1 ]
机构
[1] Chung Yuan Christian Univ, Dept Ind Engn, Chungli, Taiwan
关键词
Parallel machines; Resource-dependent processing times; Heuristics; Makespan; BIN-PACKING; JOBS; MAKESPAN; MINIMIZE; LINES;
D O I
10.1016/j.ijpe.2008.10.014
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Scheduling parallel machines with resource-dependent processing time is common in many operations management, especially in breaking processing bottlenecks in the Theory of Constraint and lean production. This study considers the problem of scheduling a set of jobs on parallel machines when the processing time of each job depends oil the amount of resource consumed. Such scheduling aims to determine the allocation of resources to jobs and jobs to machines to minimize the makespan. The problem has been proven to be NP-hard even for the fixed job processing times. This study first proposes a heuristic called CL for minimizing makespan in the parallel machines problem parallel to C-max) and then compares it with the LISTFIT heuristic of Gupta and Ruiz-Torres (2001), which is Currently regarded as the best heuristic for solving this problem. Experimental results indicate that the CL heuristic outperforms the LISTFIT heuristic in terms of solution quality and computation time. Two distinct procedures, RA1 and RA2, which optimally allocate resources with and without a fixed job sequence, respectively, are applied to evaluate the benefits of resource flexibility. Two heuristics, HI and H2, are proposed by combining the CL procedure with RA1 and RA2, respectively, to solve the problem of combining P parallel to C-max with resource allocation. Computational experiments show the average Solution quality of H2 is 99.65%, ensuring that resources Should be distributed to jobs in advance. (C) 2008 Elsevier B.V. All rights reserved.
引用
收藏
页码:256 / 266
页数:11
相关论文
共 50 条
  • [21] Machine scheduling with resource dependent processing times
    Alexander Grigoriev
    Maxim Sviridenko
    Marc Uetz
    Mathematical Programming, 2007, 110 : 209 - 228
  • [22] Machine scheduling with resource dependent processing times
    Grigoriev, Alexander
    Sviridenko, Maxim
    Uetz, Marc
    MATHEMATICAL PROGRAMMING, 2007, 110 (01) : 209 - 228
  • [23] Single-machine scheduling with learning effect and resource-dependent processing times in the serial-batching production
    Pei, Jun
    Liu, Xinbao
    Liao, Baoyu
    Pardalos, Panos M.
    Kong, Min
    APPLIED MATHEMATICAL MODELLING, 2018, 58 : 245 - 253
  • [24] Single-Machine Due-Window Assignment and Scheduling with Learning Effect and Resource-Dependent Processing Times
    Wang, Ji-Bo
    Wang, Ming-Zheng
    ASIA-PACIFIC JOURNAL OF OPERATIONAL RESEARCH, 2014, 31 (05)
  • [25] Single machine due-window assignment scheduling with resource-dependent processing times to minimise total resource consumption cost
    Liu, Lu
    Wang, Jian-Jun
    Wang, Xiao-Yuan
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2016, 54 (04) : 1186 - 1195
  • [26] Single Machine Scheduling with Resource-dependent Ready Times and Positional Deterioration Effect
    Wang, Dan
    Yin, Na
    QUANTUM, NANO, MICRO TECHNOLOGIES AND APPLIED RESEARCHES, 2014, 481 : 207 - +
  • [27] Two-machine no-wait flowshop scheduling with learning effect and convex resource-dependent processing times
    Liu, Yuelei
    Feng, Zuren
    COMPUTERS & INDUSTRIAL ENGINEERING, 2014, 75 : 170 - 175
  • [28] The no-wait two-machine flow shop scheduling problem with convex resource-dependent processing times
    Shabtay, Dvir
    Kaspi, Moshe
    Steiner, George
    IIE TRANSACTIONS, 2007, 39 (05) : 539 - 557
  • [29] Scheduling unrelated parallel machines with resource-assignable sequence-dependent setup times
    Ruiz, Ruben
    Andres-Romano, Carlos
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2011, 57 (5-8): : 777 - 794
  • [30] Scheduling unrelated parallel machines with resource-assignable sequence-dependent setup times
    Rubén Ruiz
    Carlos Andrés-Romano
    The International Journal of Advanced Manufacturing Technology, 2011, 57 : 777 - 794