Continuous earned value management with singularity functions for comprehensive project performance tracking and forecasting

被引:7
作者
Ngo, Kiet A. [1 ]
Lucko, Gunnar [1 ]
Ballesteros-Perez, Pablo [2 ]
机构
[1] Catholic Univ Amer, Dept Civil & Environm Engn, Construct Engn & Management Program, G-17 Pangborn Hall,620 Michigan Ave NE, Washington, DC 20064 USA
[2] Univ Politecn Valencia, Project Management Innovat & Sustainabil Res Ctr, Camino Vera S-N, E-46022 Valencia, Spain
关键词
Earned value management; Singularity functions; Construction projects; Continuity; Time forecasting; Cost forecasting; Performance; DURATION; INFORMATION; NETWORK;
D O I
10.1016/j.autcon.2022.104583
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Earned value management (EVM) is a classical project monitoring technique that is widely used in construction projects. Due to its simplicity, this technique suffers from limitations due to its discrete nature - activity durations, costs, and progress are gathered only at update points with no information in between. These limitations preclude EVM from being easily implemented on some project types (e.g. repetitive projects) and in conjunction with some planning techniques (e.g. linear scheduling), where information continuity is both possible and desired. Therefore, in EVM is reformulated based on singularity functions (SF). SF are a type of expressions that can be easily concatenated to model continuous inputs at the activity-level. SF are also additive so as to immediately yield project-level performance information. It is demonstrated how the complete theory of EVM is newly expressed in SF. This offers several advantages: (1) EVM metric axes can be easily swapped (allowing exact calculation of modern metrics such as Earned Schedule or the p-factor); (2) activity progress data can be inserted at any frequency as the available data allow; and (3) short-term project duration and cost forecasts are directly possible for the first time. These advantages are exemplified on a real construction project. Finally, it is discussed how the new formulation with SF produces more accurate project duration and cost estimates compared to the former discrete EVM on real construction projects.
引用
收藏
页数:10
相关论文
共 59 条
[41]  
Lipke W.H., 2003, MEASURABLE NEWS, V2003, P10
[42]   Enhancing project evaluation and review technique simulation through artificial neural network-based input modeling [J].
Lu, M .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2002, 128 (05) :438-445
[43]   Integrating Efficient Resource Optimization and Linear Schedule Analysis with Singularity Functions [J].
Lucko, Gunnar .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2011, 137 (01) :45-55
[44]   Productivity Scheduling Method: Linear Schedule Analysis with Singularity Functions [J].
Lucko, Gunnar .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2009, 135 (04) :246-253
[45]  
Macaulay W.H., 1919, MESSENGER MATH, V48, P129
[46]  
Mehrotra K., 1996, Journal of Operations Management, V14, P277, DOI 10.1016/0272-6963(96)00002-2
[47]   A fuzzy approach for the earned value management [J].
Naeni, Leila Moslemi ;
Shadrokh, Shahram ;
Salehipour, Amir .
INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2011, 29 (06) :764-772
[48]   Implementation of Earned Value Management in Unit-Price Payment Contracts [J].
Picornell, Miguel ;
Pellicer, Eugenio ;
Torres-Machi, Cristina ;
Sutrisna, Monty .
JOURNAL OF MANAGEMENT IN ENGINEERING, 2017, 33 (03)
[49]  
Pontrandolfo P., 2000, International Journal of Project Management, V18, P215, DOI 10.1016/S0263-7863(99)00015-0
[50]  
Pritsker A.AB., 1966, RM4973 NASA