The two-stage no-wait/blocking proportionate super shop scheduling problem

被引:7
作者
Koulamas, Christos [1 ]
Panwalkar, S. S. [2 ]
机构
[1] Florida Int Univ, Dept Informat Syst & Business Analyt, Miami, FL 33199 USA
[2] Johns Hopkins Univ, Carey Business Sch, Baltimore, MD USA
关键词
scheduling; dynamic programming; super shop; no wait; blocking; proportionate; ALGORITHM; MACHINE;
D O I
10.1080/00207543.2018.1518603
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
We analyze the 'no-wait' proportionate two-stage super shop scheduling problem with the objective of minimising the maximum job completion time (makespan). The existing simple sorting procedures for the open shop and the job shop do not work on the super shop. We show that the problem is still solvable in time using a procedure based on dynamic programming (DP). A unique feature of this procedure is that the state variable is defined based on the number of jobs; thus, reducing the complexity to polynomial. The same procedure solves the super shop problem with the blocking constraint. We also consider the case of machine dominance and show that the problem can be solved in linear time. Finally, we highlight the differences between the super shop with 'no-wait' and 'synchronous' processing modes via a numerical example.
引用
收藏
页码:2956 / 2965
页数:10
相关论文
共 50 条
  • [21] Scheduling Trains with Priorities: A No-Wait Blocking Parallel-Machine Job-Shop Scheduling Model
    Liu, Shi Qiang
    Kozan, Erhan
    TRANSPORTATION SCIENCE, 2011, 45 (02) : 175 - 198
  • [22] Two-stage no-wait hybrid flow-shop scheduling with sequence-dependent setup times
    Wang, Shijin
    Wang, Xiaodong
    Yu, Li
    INTERNATIONAL JOURNAL OF SYSTEMS SCIENCE-OPERATIONS & LOGISTICS, 2020, 7 (03) : 291 - 307
  • [23] No-wait two-stage flowshop problem with multi-task flexibility of the first machine
    Dong, Jianming
    Pan, Hong
    Ye, Cunkui
    Tong, Weitian
    Hu, Jueliang
    INFORMATION SCIENCES, 2021, 544 : 25 - 38
  • [24] A heuristic for no-wait flow shop scheduling
    Sapkal, Sagar U.
    Laha, Dipak
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2013, 68 (5-8) : 1327 - 1338
  • [25] A Two-Stage Cooperative Evolutionary Algorithm With Problem-Specific Knowledge for Energy-Efficient Scheduling of No-Wait Flow-Shop Problem
    Zhao, Fuqing
    He, Xuan
    Wang, Ling
    IEEE TRANSACTIONS ON CYBERNETICS, 2021, 51 (11) : 5291 - 5303
  • [26] An approximation algorithm for proportionate scheduling in the two-stage hybrid flow shop
    Dong, Jianming
    Jiang, Yiwei
    Zhang, An
    Hu, Jueliang
    Luo, Hui
    INFORMATION PROCESSING LETTERS, 2015, 115 (04) : 475 - 480
  • [27] A new two-stage constraint programming approach for open shop scheduling problem with machine blocking
    Abreu, Levi R.
    Nagano, Marcelo S.
    Prata, Bruno A.
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2023, 61 (24) : 8560 - 8579
  • [28] Cyclic flow-shop scheduling with no-wait constraints and missing operations
    Smutnicki, Czeslaw
    Pempera, Jaroslaw
    Bocewicz, Grzegorz
    Banaszak, Zbigniew
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2022, 302 (01) : 39 - 49
  • [29] Branch-and-bound and PSO algorithms for no-wait job shop scheduling
    AitZai, Abdelhakim
    Benmedjdoub, Brahim
    Boudhar, Mourad
    JOURNAL OF INTELLIGENT MANUFACTURING, 2016, 27 (03) : 679 - 688
  • [30] Semi-V-shape property for two-machine no-wait proportionate flow shop problem with TADC criterion
    Kovalev, Sergey
    Kovalyov, Mikhail Y.
    Mosheiov, Gur
    Gerstl, Enrique
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2019, 57 (02) : 560 - 566