Parallel machine, capacitated lot-sizing and scheduling for the pipe-insulation industry

被引:27
作者
de Armas, Jesica [1 ]
Laguna, Manuel [2 ]
机构
[1] Univ Pompeu Fabra, Dept Econ & Business, Barcelona, Spain
[2] Univ Colorado, Leeds Sch Business, Boulder, CO 80309 USA
关键词
scheduling; parallel machines; lot sizing; setup times; shared resources; stochastic production rates; SEQUENCE-DEPENDENT SETUP; UP CARRYOVER; MODELS; FORMULATIONS; HEURISTICS; ALGORITHMS; RESOURCES; COSTS; TIMES; CLSP;
D O I
10.1080/00207543.2019.1600763
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
We develop a solution procedure for a production problem that involves the optimal lot-sizing and scheduling of multiple products on parallel machines over a long planning horizon. The objective is to determine the product assignment, production quantities, and production sequence on each machine in order to meet demand and maximise the total production amount in a given planning horizon. We study this problem in the context of the manufacturing of pipe insulation, in which multiple features have to be considered simultaneously. The solution procedure combines mathematical programming and a post-processing sequencing heuristic. We also develop a procedure to determine safety stock levels and use Monte Carlo simulation to assess the risk associated with inventory shortages due to stochastic production rates. Computational tests are performed on both real and artificially-generated data.
引用
收藏
页码:800 / 817
页数:18
相关论文
共 58 条
  • [1] Multiple machine continuous setup lotsizing with sequence-dependent setups
    Almada-Lobo, Bernardo
    Klabjan, Diego
    Carravilla, Maria Antonia
    Oliveira, Jose F.
    [J]. COMPUTATIONAL OPTIMIZATION AND APPLICATIONS, 2010, 47 (03) : 529 - 552
  • [2] Synchronisation of scarce resources for a parallel machine lotsizing problem
    Almeder, Christian
    Almada-Lobo, Bernardo
    [J]. INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2011, 49 (24) : 7315 - 7335
  • [3] A bibliography of non-deterministic lot-sizing models
    Aloulou, Mohamed Ali
    Dolgui, Alexandre
    Kovalyov, Mikhail Y.
    [J]. INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2014, 52 (08) : 2293 - 2310
  • [4] Models for capacitated lot-sizing problem with backlogging, setup carryover and crossover
    Belo-Filho, Marcio A. F.
    Toledo, Franklina M. B.
    Almada-Lobo, Bernardo
    [J]. JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 2014, 65 (11) : 1735 - 1747
  • [5] Rolling-horizon and fix-and-relax heuristics for the parallel machine lot-sizing and scheduling problem with sequence-dependent set-up costs
    Beraldi, Patrizia
    Ghiani, Gianpaolo
    Grieco, Antonio
    Guerriero, Emanuela
    [J]. COMPUTERS & OPERATIONS RESEARCH, 2008, 35 (11) : 3644 - 3656
  • [6] Simultaneous lotsizing and scheduling problems: a classification and review of models
    Copil, Karina
    Woerbelauer, Martin
    Meyr, Herbert
    Tempelmeier, Horst
    [J]. OR SPECTRUM, 2017, 39 (01) : 1 - 64
  • [7] A new dantzig-wolfe reformulation and branch-and-price algorithm for the capacitated lot-sizing problem with setup times
    Degraeve, Zeger
    Jans, Raf
    [J]. OPERATIONS RESEARCH, 2007, 55 (05) : 909 - 920
  • [8] A review of discrete-time optimization models for tactical production planning
    Diaz-Madronero, Manuel
    Mula, Josefa
    Peidro, David
    [J]. INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2014, 52 (17) : 5171 - 5205
  • [9] SOLVING MULTI-ITEM CAPACITATED LOT-SIZING PROBLEMS USING VARIABLE REDEFINITION
    EPPEN, GD
    MARTIN, RK
    [J]. OPERATIONS RESEARCH, 1987, 35 (06) : 832 - 848
  • [10] An analysis of formulations for the capacitated lot sizing problem with setup crossover
    Fiorotto, Diego Jacinto
    Jans, Raf
    de Araujo, Silvio Alexandre
    [J]. COMPUTERS & INDUSTRIAL ENGINEERING, 2017, 106 : 338 - 350