Numerical investigation of the failure of a shotcrete lining

被引:0
|
作者
Poettler, R. [1 ]
机构
[1] ILF Consulting Engineers, Rum Innsbruck, Austria
来源
Numerical Methods in Geotechnical Engineering | 2006年
关键词
D O I
暂无
中图分类号
P5 [地质学];
学科分类号
0709 ; 081803 ;
摘要
In the course of a 7-km-long railway tunnel, which is situated mainly in weathered chalk marl, covered by Tertiary over a length of about 500 m, the tunnel traverses a transition zone of chalk marl, weathered chalk marl and Tertiary. In a specific area with a length of 100 m, the deformation during tunnel drive did not cease and exceeded the predicted values considerably About one year after the installation of the primary lining, cracks occurred in the shotcrete lining of the invert. Many different geotechnical models have been discussed to explain this special ground behaviour and the failure. Numerical calculations based on extensive geotechnical investigations were performed, aiming at detecting the cause of this failure. It was only when the real ground behaviour and reasons of failure had been understood that the secondary lining could be designed in an optimised way.
引用
收藏
页码:313 / 318
页数:6
相关论文
共 50 条
  • [1] Shotcrete as final lining for tunnels
    Palermo, G
    Helene, PRDL
    TUNNELS AND METROPOLISES, VOLS 1 AND 2, 1998, : 349 - 354
  • [2] SHOTCRETE FOR TUNNEL LINING.
    Gullan, G.T.
    Tunnels and Tunnelling, 1975, 7 (05):
  • [3] Factors of shotcrete lining design
    John, Max
    Mattle, Bruno
    Tunnels and Tunnelling International, 2003, 35 (10): : 42 - 44
  • [4] Experimental and Numerical Investigation of Particle Kinematics in Shotcrete
    Ginouse, Nicolas
    Jolin, Marc
    JOURNAL OF MATERIALS IN CIVIL ENGINEERING, 2014, 26 (11)
  • [5] Laboratory tests and numerical modelling of strength-deformation parameters of a shotcrete lining
    Prusek, Stanislaw
    Rotkegel, Marek
    Malecki, Lukasz
    ENGINEERING STRUCTURES, 2014, 75 : 353 - 362
  • [6] Numerical Analysis of TBM Tunnel Lining Behavior using Shotcrete Constitutive Model
    Shaalan, Heyam H.
    Azit, Romziah
    Ismail, Mohd Ashraf Mohamad
    CIVIL ENGINEERING JOURNAL-TEHRAN, 2018, 4 (05): : 1046 - 1065
  • [7] Time factor in shotcrete lining design
    Peila, D
    Pelizza, S
    Oreste, PP
    TUNNELS AND METROPOLISES, VOLS 1 AND 2, 1998, : 343 - 348
  • [8] Numerical Study on the Mechanical Behavior of Shotcrete Lining with Yielding Support in Large Deformation Tunnel
    Yang, Kai
    Yan, Qixiang
    Shi, Zhendong
    Zhang, Chuan
    Ma, Shuqi
    ROCK MECHANICS AND ROCK ENGINEERING, 2023, 56 (02) : 1563 - 1584
  • [9] Shotcrete lining of South Deep shafts
    Erasmus, WP
    Swanepoel, CD
    Munro, D
    Hague, I
    Northcroft, I
    Parrish, A
    Bassett, A
    JOURNAL OF THE SOUTH AFRICAN INSTITUTE OF MINING AND METALLURGY, 2001, 101 (04): : 169 - 176
  • [10] Shotcrete as a tunnel lining - A laboratory study
    Chang, YT
    Stille, H
    EIGHTH INTERNATIONAL CONGRESS ON ROCK MECHANICS, VOL 3, PROCEEDINGS, 1997, : 1305 - 1307