A heuristic approach to minimizing the waiting time of jobs in two-stage flow shop scheduling

被引:0
|
作者
Goyal, Bharat [1 ]
Kaur, Sukhmandeep [2 ]
Gupta, Deepak [3 ]
机构
[1] Gen Shivdev Singh Diwan Gurbachan Singh Khalsa Col, Dept Math, Patiala, Punjab, India
[2] Punjabi Univ, Dept Math, Patiala, Punjab, India
[3] Maharishi Markandeshwar Univ, Dept Math, Mullana, Haryana, India
关键词
special structures; FSS; waiting time; processing time; heuristic;
D O I
10.37190/ord240109
中图分类号
C93 [管理学]; O22 [运筹学];
学科分类号
070105 ; 12 ; 1201 ; 1202 ; 120202 ;
摘要
The paper presents the influence of the waiting time of jobs in a 2 machine k -job Flow Shop Scheduling (FSS) problem. The main intention of the study is to find a sequence of jobs that delivers the least sum of the time of waiting for jobs. A heuristic approach has been adopted to achieve the desired objective. The experiments are conducted for more than 2000 problems of various sizes for the problems with special structures and problems with random times of processing. The weighted mean absolute error (WMAE) for the average of the sum of the waiting times of jobs is computed for both kind of problems after comparing with the optimal solutions. WMAE has been obtained less than 0.0075 for problems with special structures and less than 0.087 for problems with random times of processing. The WMAE is also reducing significantly with the increase in job size. The results demonstrate that the presented step-by-step procedure of the heuristic delivers significantly close to optimal solutions.
引用
收藏
页码:175 / 191
页数:17
相关论文
共 50 条
  • [1] Minimizing makespan in a two-stage hybrid flow shop scheduling problem with open shop in one stage
    Dong Jian-ming
    Hu Jue-liang
    Chen Yong
    APPLIED MATHEMATICS-A JOURNAL OF CHINESE UNIVERSITIES SERIES B, 2013, 28 (03) : 358 - 368
  • [2] Minimizing makespan in a two-stage hybrid flow shop scheduling problem with open shop in one stage
    Jian-ming Dong
    Jue-liang Hu
    Yong Chen
    Applied Mathematics-A Journal of Chinese Universities, 2013, 28 : 358 - 368
  • [3] Minimizing makespan in a two-stage hybrid flow shop scheduling problem with open shop in one stage
    DONG Jianming
    HU Jueliang
    CHEN Yong
    AppliedMathematics:AJournalofChineseUniversities(SeriesB), 2013, 28 (03) : 358 - 368
  • [4] A two-stage flow-shop scheduling problem with incompatible job families and limited waiting time
    Li, Yonglin
    Dai, Zhenhua
    ENGINEERING OPTIMIZATION, 2020, 52 (03) : 484 - 506
  • [5] RULE BASED HEURISTIC APPROACH FOR MINIMIZING TOTAL FLOW TIME IN PERMUTATION FLOW SHOP SCHEDULING
    Rathinam, Balasundaram
    Govindan, Kannan
    Neelakandan, Baskar
    Raghavan, Siva Sankar
    TEHNICKI VJESNIK-TECHNICAL GAZETTE, 2015, 22 (01): : 25 - 32
  • [6] Heuristic algorithm for two-stage flexible flow shop scheduling with tail group constraint
    Li, Zhantao
    Chen, Qingxin
    Mao, Ning
    Jixie Gongcheng Xuebao/Journal of Mechanical Engineering, 2013, 49 (12): : 183 - 192
  • [7] Heuristic algorithms for multiprocessor task scheduling in a two-stage hybrid flow-shop
    Oguz, C
    Ercan, MF
    Cheng, TCE
    Fung, YF
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2003, 149 (02) : 390 - 403
  • [8] A heuristic algorithm for two-stage flexible flow shop scheduling with head group constraint
    Li, Zhan-tao
    Chen, Qing-xin
    Mao, Ning
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2013, 51 (03) : 751 - 771
  • [9] Heuristic algorithms for two-stage flexible flow shop scheduling with head group constraint
    Li, Zhantao
    Chen, Qingxin
    Mao, Ning
    Jixie Gongcheng Xuebao/Journal of Mechanical Engineering, 2012, 48 (22): : 189 - 198
  • [10] Distributed two-stage hybrid flow shop scheduling
    Zhang Q.
    Sun Z.
    Lei D.
    Huazhong Keji Daxue Xuebao (Ziran Kexue Ban)/Journal of Huazhong University of Science and Technology (Natural Science Edition), 2020, 48 (04): : 127 - 132