Early warning system for highway construction projects using GA-SVM

被引:9
作者
Shafaat, Ali [1 ]
Marbouti, Farshid [2 ]
Mahfouz, Tarek [3 ]
机构
[1] Shahid Beheshti Univ, Fac Architecture & Urban Design, Tehran, Iran
[2] San Jose State Univ, Charles W Davidson Coll Engn, San Jose, CA 95192 USA
[3] Ball State Univ, Dept Construct Management & Interior Design, Muncie, IN 47306 USA
关键词
Data mining; SVM; change; early warning; genetic algorithm; prediction; SUPPORT VECTOR MACHINE; MODEL; COST; MANAGEMENT; PERFORMANCE; IMPACT; RISK;
D O I
10.1080/15623599.2022.2056805
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Construction project changes vis-a-vice their impact on the cost and time performance has been the main concern of practitioners and scholars for decades; hence, many attempts have been made to develop early warning mechanisms for decision-makers. Since many factors drive project changes, various strategies can be adopted to mitigate further alterations after awarding the contract. This study aimed at developing multiple Support Vector Machine (SVM) classifiers to enhance change prediction accuracy. 5,628 completed construction-oriented projects datasets comprising preconstruction information, obtained from the Indiana Department of Transportation (INDOT), were used to develop the models. All free kernel parameters were determined using Genetic Algorithm (GA) optimization. The results show that the models built using SVM classifiers with Radial Basis Function (RBF) kernel function were successful in decreasing the uncertainty associated with change order occurrence in the early phases of the projects. Therefore, the study recommends that agencies, developers, and contractors store historical project data to build early warning systems using machine learning techniques.
引用
收藏
页码:2348 / 2357
页数:10
相关论文
共 65 条
[1]   Project Delivery Methods' Change-Order Types and Magnitudes Experienced in Highway Construction [J].
Alleman, Douglas ;
Antoine, Arthur L. C. ;
Stanford, M. Scott ;
Molenaar, Keith R. .
JOURNAL OF LEGAL AFFAIRS AND DISPUTE RESOLUTION IN ENGINEERING AND CONSTRUCTION, 2020, 12 (02)
[2]   Application of support vector machines in assessing conceptual cost estimates [J].
An, Sung-Hoon ;
Park, U-Yeol ;
Kang, Kyung-In ;
Cho, Moon-Young ;
Cho, Hun-Hee .
JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2007, 21 (04) :259-264
[3]   Frequency of Change Orders in Highway Construction Using Alternate Count-Data Modeling Methods [J].
Anastasopoulos, Panagiotis Ch. ;
Labi, Samuel ;
Bhargava, Abhishek ;
Bordat, Claire ;
Mannering, Fred .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2010, 136 (08) :886-893
[4]  
[Anonymous], 2000, Construction Management and Economics, DOI [10.1080/01446190050024897, DOI 10.1080/01446190050024897]
[5]   MANAGING STRATEGIC SURPRISE BY RESPONSE TO WEAK SIGNALS [J].
ANSOFF, HI .
CALIFORNIA MANAGEMENT REVIEW, 1975, 18 (02) :21-33
[6]   Forecasting contractor's deviation from the client objectives in prequalification model using support vector regression [J].
Attar, Amirhossein Movahedian ;
Khanzadi, Mostafa ;
Dabirian, Shahin ;
Kalhor, Elmira .
INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2013, 31 (06) :924-936
[7]   Bidding for Incomplete Contracts: An Empirical Analysis of Adaptation Costs [J].
Bajari, Patrick ;
Houghton, Stephanie ;
Tadelis, Steven .
AMERICAN ECONOMIC REVIEW, 2014, 104 (04) :1288-1319
[8]  
Bordat C., 2004, ANAL COST OVERRUNS T
[9]  
Bower D., 2000, Construction Management and Economics, V18, P263, DOI DOI 10.1080/014461900370636
[10]   Statistical modeling: The two cultures [J].
Breiman, L .
STATISTICAL SCIENCE, 2001, 16 (03) :199-215