Geomechanical characterization of rock mass rating and numerical modeling for underground mining excavation design

被引:2
作者
Kimour, Mohamed [1 ]
Boukelloul, Mohamed L. [2 ]
Hafsaoui, Abdallah [3 ]
Narsis, S. [4 ]
Benghadab, Khadouja M. [5 ]
Benselhoub, Aissa [4 ]
机构
[1] Badji Mokhtar Univ, Dept Min, Lab Phys Met & Properties Mat, BP 12, Annaba 23000, Algeria
[2] Badji Mokhtar Univ, Dept Min, Lab Mineral Proc Resources & Environm, BP 12, Annaba 23000, Algeria
[3] Badji Mokhtar Univ, Dept Min, Nat Resources & Planning Lab, BP 12, Annaba 23000, Algeria
[4] Environm Res Ctr CRE, Annaba, Algeria
[5] Badji Mokhtar Univ, Lab Met & Mat Sci, Annaba, Algeria
来源
JOURNAL OF GEOLOGY GEOGRAPHY AND GEOECOLOGY | 2023年 / 32卷 / 01期
关键词
Geomechanics; Characterization; Mining; RMR; FEM; Underground excavation; Tunnel; RMR; SYSTEM;
D O I
10.15421/112308
中图分类号
P [天文学、地球科学];
学科分类号
07 ;
摘要
The objective of the study is the geomechanical characterization of the rock mass rating RMR system and numerical modeling for mining underground excavation design of the Djebel El Ouahch tunnel, in Constantine (Algeria).The geological and geotechnical character- ization of the rock mass is important for the design of underground mining excavations. In this article, we present the results of the RMR characterization of the rock mass and the numerical modeling by the finite element method (FEM), under the conditions of the Djebel El Ouahch tunnel, Constantine (Algeria).The RMR system is a useful tool for characteriza- tion of the rock mass quality and establishing the appropriate support system. For poor rock (Class IV), the excavation should be top heading and bench 1.0 m - 1.5 m advance in top heading. Support should be installed concurrently with excavation, 10 m from face. Rock bolting should be systematic with 4 m - 5 m long, spaced 1.5 m - 1.5 m in the crown and walls with wire mesh, Shotcrete of 100 m-150 mm in the crown and 100 mm in sides. The steel sets should be light to medium ribs spaced 1.5 m only when required. The rock mass consists of generally poor rocks with average stand-up time of 10 hours for 2.5m span with mass cohesion ranges between 100 kPa - 200 kPa and rock mass friction angle ranges from 15 degrees to 35 degrees. The FEM project due to its precision calculates the safety factor and evaluates the principal deformations and displacements of the rocks mass .The originality of this work lies in the use of two different approaches , the RMR system and numerical method (FEM) for analyzing the quality and evaluation of the deformations and displace- ments of rock mass .This method has become a very common practice in underground mining excavation design.This study illustrates that the results obtained by RMR of the argillite rock mass in the case is 28.00 ,ranging from 21.0 to 40.0 classified as Class IV (Poor Rock), while the results of FEM reveal that in accordance with the poor quality of the rocks, large deformations and displacements were observed around the underground mining excavation, which can be at the origin of the ruptures. The value of the safety factor of the order of 0.95 to 1.24 shows the instability of the excavation, and the appearance of very considerable hazard zones in the argillite layer.
引用
收藏
页码:67 / 78
页数:12
相关论文
共 22 条
[1]   Numerical analysis of reducing tunneling effect on viaduct piles foundation by jet grouted wall [J].
Asker, Kamel ;
Fouad, Mohmed Tarek ;
Bahr, Mohamed ;
El-Attar, Ahmed .
MINING OF MINERAL DEPOSITS, 2021, 15 (01) :75-86
[2]  
Barton N., 2008, RMR and Q - Setting records
[3]  
Berkane A., 2018, ASIAN J CIVILENGINEE, V19, P913, DOI [10.1007/s42107-018-0072-x, DOI 10.1007/S42107-018-0072-X]
[4]  
Bieniawski ZT, 1989, Engineering rock mass classifications
[5]   Simple three-dimensional Mohr-Coulomb criteria for intact rocks [J].
Jiang, Hua .
INTERNATIONAL JOURNAL OF ROCK MECHANICS AND MINING SCIENCES, 2018, 105 :145-159
[6]   Weightage Effect during Back-Calculation of Rock-Mass Quality from the Installed Tunnel Support in Rock-Mass Rating and Tunneling Quality Index System [J].
Kim, Jonguk ;
Rehman, Hafeezur ;
Ali, Wahid ;
Naji, Abdul Muntaqim ;
Yoo, Hankyu .
APPLIED SCIENCES-BASEL, 2019, 9 (10)
[7]  
Magomedov I.A., 2020, ICMSIT J PHYS C SERI, V1515, DOI [10.1088/17426596/1515/3/032073, DOI 10.1088/17426596/1515/3/032073]
[8]   On the use of the RMR system for estimation of rock mass deformation modulus [J].
Nejati, Hamid Reza ;
Ghazvinian, Abdolhadi ;
Moosavi, Seyed Amin ;
Sarfarazi, Vahab .
BULLETIN OF ENGINEERING GEOLOGY AND THE ENVIRONMENT, 2014, 73 (02) :531-540
[9]   Alternative Software for Evaluating Preliminary Rock Stability of Tunnel using Rock Mass Rating (RMR) and Rock Mass Quality (Q) on Android Smartphone [J].
Pantaweesak, Pantawee ;
Sontamino, Phongpat ;
Tonnayopas, Danupon .
ENGINEERING JOURNAL-THAILAND, 2019, 23 (01) :95-108
[10]   Rock quality designation (RQD): time to rest in peace [J].
Pells, P. J. ;
Bieniawski, Z. T. ;
Hencher, S. R. ;
Pells, S. E. .
CANADIAN GEOTECHNICAL JOURNAL, 2017, 54 (06) :825-834