MULTI-OBJECTIVE ROBUST PRODUCTION PLANNING CONSIDERING WORKFORCE EFFICIENCY WITH A METAHEURISTIC SOLUTION APPROACH

被引:2
作者
Zeidabadi, Sepideh Asadi [1 ]
Nik, Ebrahim Rezaee [1 ]
Hejazi, Taha-Hossein [2 ]
机构
[1] Sadjad Univ Technol Mashhad, Dept Ind Engn, Mashhad, Iran
[2] Amirkabir Univ Technol, Dept Ind Engn, Garmsar Campus, Garmsar, Iran
来源
INTERNATIONAL JOURNAL OF INDUSTRIAL ENGINEERING-THEORY APPLICATIONS AND PRACTICE | 2023年 / 30卷 / 01期
关键词
Multi-objective Production Planning; Robust Optimization; Workforce Efficiency; Non-dominated Sorting Genetic Algorithm-II; Strength Pareto Evolutionary Algorithm 2; Pareto Envelope-based Selection Algorithm II; LOOP SUPPLY CHAIN; OPTIMIZATION MODEL; NSGA-II; NETWORK; DEMAND;
D O I
10.23055/ijietap.2023.30.1.6995
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Timely delivery of products to customers is one of the main factors of customer satisfaction and a key to the survival of a manufacturing system. Therefore, decreasing wasted time in manufacturing processes significantly affects production delivery time, which can be achieved through the maximization of workforce efficiency. This issue becomes more complicated when the parameters of the production system are under uncertainty. This paper presents a bi-objective scenario -based robust production planning model considering maximizing workforce efficiency and minimizing costs where the backorder, demand, and costs are uncertain. Also, backorder, raw materials purchasing, inventory control, and manufacturing time capacity are considered. A case study in a faucet manufacturing plant is considered to solve the model. Furthermore, the epsilon-constraint method, the Non-dominated Sorting Genetic Algorithm-II (NSGA-II), the Strength Pareto Evolutionary Algorithm 2 (SPEA2), and the Pareto Envelope-based Selection Algorithm II (PESA-II) are employed to solve the model. Also, the Taguchi method is used to tune the parameters of these algorithms. To compare these algorithms, five indicators are defined. The results show that the SPEA2 is the most time-consuming algorithm and the NSGA-II is the fastest, while their objective function values are nearly the same.
引用
收藏
页码:32 / 50
页数:19
相关论文
共 33 条
[1]   Robust design of a multi-objective closed-loop supply chain by integrating on-time delivery, cost, and environmental aspects, case study of a Tire Factory [J].
Abdolazimi, Omid ;
Esfandarani, Mitra Salehi ;
Salehi, Maryam ;
Shishebori, Davood .
JOURNAL OF CLEANER PRODUCTION, 2020, 264
[2]   A multi-objective robust optimization model for multi-product multi-site aggregate production planning in a supply chain under uncertainty [J].
Al-e-hashem, S. M. J. Mirzapour ;
Malekly, H. ;
Aryanezhad, M. B. .
INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2011, 134 (01) :28-42
[3]   An efficient algorithm to solve a multi-objective robust aggregate production planning in an uncertain environment [J].
Al-e-Hashem, Seyed Mohamad Javad Mirzapour ;
Aryanezhad, Mir Bahador ;
Sadjadi, Seyed Jafar .
INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2012, 58 (5-8) :765-782
[4]   A robust integrated production and preventive maintenance planning model for multi-state systems with uncertain demand and common cause failures [J].
Alimian, Mahyar ;
Saidi-Mehrabad, Mohammad ;
Jabbarzadeh, Armin .
JOURNAL OF MANUFACTURING SYSTEMS, 2019, 50 :263-277
[5]   An integrated multi-echelon robust closed-loop supply chain under imperfect quality production [J].
Almaraj, Ismail I. ;
Trafalis, Theodore B. .
INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2019, 218 :212-227
[6]  
[Anonymous], 2007, Evolutionary algorithms for solving multi-objective problems
[7]   A cross-docking scheduling problem with sub-population multi-objective algorithms [J].
Arabani, A. Boloori ;
Zandieh, M. ;
Ghomi, S. M. T. Fatemi .
INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2012, 58 (5-8) :741-761
[8]   A multi-phase covering Pareto-optimal front method to multi-objective scheduling in a realistic hybrid flowshop using a hybrid metaheuristic [J].
Behnamian, J. ;
Ghomi, S. M. T. Fatemi ;
Zandieh, M. .
EXPERT SYSTEMS WITH APPLICATIONS, 2009, 36 (08) :11057-11069
[9]   Robust multi-echelon multi-period inventory control [J].
Ben-Tal, Aharon ;
Golany, Boaz ;
Shtern, Shimrit .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2009, 199 (03) :922-935
[10]  
Corne D. W., 2001, GECCO 01, P283, DOI DOI 10.5555/2955239.2955289