Risk Assessment of Immersed Tube Tunnel Construction

被引:6
作者
Dong, Sihui [1 ]
Li, Shiqun [1 ]
Yu, Fei [1 ]
Wang, Kang [1 ]
机构
[1] Dalian Jiaotong Univ, Sch Traff & Transportat Engn, Dalian 116028, Peoples R China
关键词
tunnel construction by immersed tube method; analytic hierarchy process; genetic algorithm; cloud model theory; risk assessment; risk control; QUALITY; DESIGN;
D O I
10.3390/pr11040980
中图分类号
TQ [化学工业];
学科分类号
0817 ;
摘要
Due to the complexity of risk factors in constructing immersed tube tunnels, it is impossible to accurately identify risks. To solve this problem, and the uncertainty and fuzziness of risk factors, a risk assessment method for immersed tube tunnel construction was proposed based on WBS-RBS (Work Breakdown Structure-Risk Breakdown Structure), improved AHP (analytic hierarchy process), and cloud model theory. WBS-RBS was used to analyze the risk factors of immersed tube tunnel construction from the aspects of the construction process and 4M1E, and built a more comprehensive and accurate construction risk index system. The weight of each index was calculated by the improved AHP of a genetic algorithm. The cloud model theory was used to build the cloud map of risk assessment for immersed tunnel construction and evaluate construction risk. Taking the Dalian Bay subsea tunnel project as an example, the risk assessment method of immersed tunnel construction was verified. The results showed that this method not only solved the problem of failing the consistency check in the higher-order judgment matrix but also improved the consistency pass rate by 33.3% and accurately reflected the risk assessment results. The assessment results show that the construction risk level of the Dalian Bay submarine-immersed tunnel is medium. The risk level of indicators "slope instability" and "water-stop damage" are high risk, while "pipe section cracking", "low underwater alignment accuracy", "uneven crimping of a water-stop", and "uneven substrate treatment" are medium risk. This provides a reference for the risk assessment study of immersed tunnel construction.
引用
收藏
页数:13
相关论文
共 26 条
  • [1] Design, construction and monitoring of an underwater retaining wall close to an existing immersed tunnel
    Bauduin, C.
    Kirstein, A. A.
    [J]. TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2022, 120
  • [2] Design and construction of the Oresund tunnel
    Busby, J
    Marshall, C
    [J]. PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-CIVIL ENGINEERING, 2000, 138 (04) : 157 - 166
  • [3] Dong MY, 2017, PROCEEDINGS OF 2017 6TH INTERNATIONAL CONFERENCE ON COMPUTER SCIENCE AND NETWORK TECHNOLOGY (ICCSNT 2017), P380, DOI 10.1109/ICCSNT.2017.8343723
  • [4] Finite element analysis and optimization of tractor gearbox body under various kinds of working conditions
    Dong, Sihui
    Li, Shiqun
    Fu, Shenghui
    Wang, Kang
    [J]. SCIENTIFIC REPORTS, 2022, 12 (01)
  • [5] Safety evaluation of rail transit vehicle system based on improved AHP-GA
    Dong, Sihui
    Yu, Fei
    Wang, Kang
    [J]. PLOS ONE, 2022, 17 (08):
  • [6] A virtual simulation experiment platform of subway emergency ventilation system and study on its teaching effect
    Dong, Sihui
    Yu, Fei
    Wang, Kang
    [J]. SCIENTIFIC REPORTS, 2022, 12 (01)
  • [7] Fu Bin, 2011, Application Research of Computers, V28, P420, DOI 10.3969/j.issn.1001-3695.2011.02.004
  • [8] Gao Z., 2019, P INT C AS PAC COAST, P331
  • [9] Ji HM, 2019, PROCEEDINGS OF 2019 IEEE 8TH JOINT INTERNATIONAL INFORMATION TECHNOLOGY AND ARTIFICIAL INTELLIGENCE CONFERENCE (ITAIC 2019), P754, DOI [10.1109/ITAIC.2019.8785869, 10.1109/itaic.2019.8785869]
  • [10] [姜伟 Jiang Wei], 2020, [中国公路学报, China Journal of Highway and Transport], V33, P114