Development and validation of a framework for preventing and mitigating construction delay using 4D BIM platform in Bangladeshi construction sector

被引:17
作者
Assafi, Mohammad Nafe [1 ]
Hossain, Md Mehrab [2 ]
Chileshe, Nicholas [3 ,4 ]
Datta, Shuvo Dip [2 ]
机构
[1] Mississippi State Univ, Dept Civil & Environm Engn, Mississippi State, MS USA
[2] Khulna Univ Engn & Technol, Dept Bldg Engn & Construct Management, Khulna, Bangladesh
[3] Univ South Australia, Sustainable Infrastruct & Resource Management SIR, UniSA STEM, Adelaide, SA, Australia
[4] Univ Johannesburg, Fac Engn & Built Environm, Johannesburg, South Africa
来源
CONSTRUCTION INNOVATION-ENGLAND | 2023年 / 23卷 / 05期
关键词
Bangladesh; Building information modeling (BIM); Construction delay; 4D BIM; 4D TimeLiner tool; Clash detective tool; SIMULATION;
D O I
10.1108/CI-08-2021-0160
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Purpose As a developing nation, Bangladesh still has scarce technological applications in the construction sector, which results in construction delays. This paper aims to propose a framework that will diminish manual labor, reduce human error and apply four-dimensional (4D) building information modeling (BIM)-based solutions to mitigate and prevent construction project delays. Design/methodology/approach First, a systematic literature review was conducted on analyzing the construction delay scenario in the context of Bangladesh and other countries. Next, a 4D BIM-based framework was developed using Autodesk Navisworks Manage. Finally, it was used to run on-site simulations on an ongoing construction project which faced delays because of design errors and inefficient planning. Findings Affirmative results were found from applying these methods through real-time project simulation. The current status of the project and the status after using BIM technology were compared. It was observed that during both the preconstruction and execution phases, the application of 4D BIM could reduce the delay posed by design error and inefficient planning. Practical implications The project manager and the design engineers can use these frameworks to review their projects. For the design engineers, the preconstruction phase portion of the framework will help identify the probable errors in the design. For the project managers, keeping track of time using the execution phase portion of the framework will be resourceful. Originality/value To the best of the authors' knowledge, this study is the first to assess the significant delay factors endemic in Bangladesh and develop a BIM-based technological solution. This study is solely dedicated to reforming the construction techniques in Bangladesh through the application of 4D BIM technology.
引用
收藏
页码:1255 / 1278
页数:24
相关论文
共 75 条
[1]   Building Information Modelling (BIM) adoption and implementation enablers in AEC firms: a systematic literature review [J].
Abbasnejad, Behzad ;
Nepal, Madhav Prasad ;
Ahankoob, Alireza ;
Nasirian, Araz ;
Drogemuller, Robin .
ARCHITECTURAL ENGINEERING AND DESIGN MANAGEMENT, 2021, 17 (5-6) :411-433
[2]   Analysis of cost and schedule performance of international development projects [J].
Ahsan, Kamrul ;
Gunawan, Indra .
INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2010, 28 (01) :68-78
[3]  
Al Amin A., 2020, SEU Journal of Science and Engineering, V14, P1
[4]   A project control process in pre-construction phases Focus on effective methodology [J].
Al-Reshaid, Khaled ;
Kartam, Nabil ;
Tewari, Narendra ;
Al-Bader, Haya .
ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2005, 12 (04) :351-+
[5]   Ranking of the Factors Causing Cost Overrun in Infrastructural Projects of UAE [J].
Alhammadi, Ahmed Salem Ahmed Marey ;
Memon, Aftab Hameed .
INTERNATIONAL JOURNAL OF SUSTAINABLE CONSTRUCTION ENGINEERING AND TECHNOLOGY, 2020, 11 (02) :204-211
[6]  
[Anonymous], 2007, AD BIM FAC MAN SOL M
[7]   Causes of delay in large construction projects [J].
Construction Engineering and Management Department, King Fahd University of Petroleum and Minerals, Box # 680, Dhahran, 31261, Saudi Arabia .
Int. J. Proj. Manage., 2006, 4 (349-357) :349-357
[8]   Investigating the causes of construction delay on the perspective of organization-sectors involved in the construction industry of Bangladesh [J].
Assafi, Mohammad Nafe ;
Hoque, Md Ikramul ;
Hossain, Md Mehrab .
INTERNATIONAL JOURNAL OF BUILDING PATHOLOGY AND ADAPTATION, 2024, 42 (04) :788-817
[9]  
Azhar S., 2011, Leadership and Management in Engineering, V11, P241, DOI [DOI 10.1061/(ASCE)LM.1943-5630.0000127, 10.1061/(ASCE)LM.1943-5630.0000127]
[10]   Empirical study of schedule delay in Moroccan construction projects [J].
Bajjou, Mohamed Saad ;
Chafi, Anas .
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2020, 20 (07) :783-800