Active Distribution Network Expansion Planning With Dynamic Thermal Rating of Underground Cables and Transformers

被引:11
作者
Li, Yinxiao [1 ]
Chen, Qixin [1 ]
Strbac, Goran [2 ]
Hur, Kyeon [3 ]
Kang, Chongqing [1 ]
机构
[1] Tsinghua Univ, Dept Elect Engn, State Key Lab Power Syst, Beijing 100084, Peoples R China
[2] Imperial Coll London, Dept Elect & Elect Engn, London SW7 2AZ, England
[3] Yonsei Univ, Sch Elect & Elect Engn, Seoul 03722, South Korea
基金
中国国家自然科学基金;
关键词
Active distribution networks; distribution network expansion planning; dynamic thermal rating; under-ground cable; transformer; TRANSMISSION EXPANSION; OPTIMIZATION; DISPATCH; SYSTEM; MODEL; FLOW;
D O I
10.1109/TSG.2023.3266782
中图分类号
TM [电工技术]; TN [电子技术、通信技术];
学科分类号
0808 ; 0809 ;
摘要
The rapid development of renewable distributed generation in active distribution networks (ADNs) imposes an increasing burden on the transfer capability of the ADNs, bringing new challenges to the distribution network expansion planning (DNEP) problem. Dynamic thermal rating (DTR), which evaluates the equipment rating based on the actual weather conditions and equipment thermal states, can enhance the equipment transfer capability to support the integration of renewable distributed generation. In this paper, we propose a DNEP model of ADNs incorporating the DTR of cables and transformers, given that underground cable feeder is preferred in the rapid urbanization trends. Then, we derive a linear reformulation of the original DNEP model and propose a modified Benders decomposition (MBD) algorithm to solve the DNEP model. To select more effective representative day scenarios, we propose a cost-based clustering method for representative day selection applicable to solving the DNEP model. Case studies based on the IEEE 33-node system and the PG&E 69-node system show that the implementation of DTR saves 14.7% and 15.1% of the investment costs of the two systems respectively. The effectiveness of the MBD algorithm and the cost-based clustering method is also verified by the case studies.
引用
收藏
页码:218 / 232
页数:15
相关论文
共 50 条
[1]  
[Anonymous], 2014, IEC 60287-1-1
[2]  
[Anonymous], 2015, IEC Standard 60287-2-1
[3]  
[Anonymous], 2012, IEEE StandardC57.91-2011 (Revision of IEEE Standard C57.91-1995
[4]  
[Anonymous], 2016, Smart grid to enhance power transmission in Vietnam
[5]  
[Anonymous], 2020, Innovation landscape brief: Dynamic line rating
[6]  
[Anonymous], 2022, Distribution zone substation data
[7]   OPTIMAL CAPACITOR PLACEMENT ON RADIAL-DISTRIBUTION SYSTEMS [J].
BARAN, ME ;
WU, FF .
IEEE TRANSACTIONS ON POWER DELIVERY, 1989, 4 (01) :725-734
[8]   NETWORK RECONFIGURATION IN DISTRIBUTION-SYSTEMS FOR LOSS REDUCTION AND LOAD BALANCING [J].
BARAN, ME ;
WU, FF .
IEEE TRANSACTIONS ON POWER DELIVERY, 1989, 4 (02) :1401-1407
[9]   On polyhedral approximations of the second-order cone [J].
Ben-Tal, A ;
Nemirovski, A .
MATHEMATICS OF OPERATIONS RESEARCH, 2001, 26 (02) :193-205
[10]   Partitioning procedures for solving mixed-variables programming problems [J].
Benders, J. F. .
COMPUTATIONAL MANAGEMENT SCIENCE, 2005, 2 (01) :3-19