Study on the Stress Distribution and Stability Control of Surrounding Rock of Reserved Roadway with Hard Roof

被引:5
作者
Hao, Yuxi [1 ]
Li, Mingliang [1 ]
Wang, Wen [2 ]
Zhang, Zhizeng [1 ]
Li, Zhun [1 ]
机构
[1] Zhongyuan Univ Technol, Sch Architectural Engn, Zhengzhou 450007, Peoples R China
[2] Henan Polytech Univ, Coll Energy Sci & Engn, Jiaozuo 454000, Peoples R China
关键词
reserved roadway; roof cutting and pressure releasing; surrounding rock damage; hard roof; grouting anchor; COAL-MINE;
D O I
10.3390/su151914111
中图分类号
X [环境科学、安全科学];
学科分类号
08 ; 0830 ;
摘要
According to field observation and theoretical analysis, the failure of the 1523103 reserved roadway is mainly affected by the lateral support pressure, rock mass strength, and support mode. With the mining of the 152309 working face, the lateral pressure of coal pillars on both sides of the reserved roadway increases, and since the lithology of the two sides and the floor of the roadway is weak, the reserved roadway experiences spalling and floor heave. Through numerical simulation, the distribution law of surrounding rock stress and the displacement of surrounding rock are obtained after the roof cutting and pressure relief of the reserved roadway with hard roof. According to the cause of surrounding rock failure of a reserved roadway, the combined control technology of roof cutting and pressure relief, grouting anchor cable support, and bolt support is put forward. After cutting the roof and releasing the pressure on the working face, the lateral support pressure of the two sides of the roadway is significantly reduced, the deformation of the two sides of the roadway is small, the maximum shrinkage rate of the section is reduced from 70% to 11%, and the deformation of the surrounding rock of the 1523103 reserved roadway is effectively controlled. The successful control of the surrounding rock in the 1523103 tunnel reduces the number of coal pillars to be installed, improves the coal extraction rate, and is conducive to the sustainable utilization of limited natural resources and the sustainable development of the coal industry.
引用
收藏
页数:21
相关论文
共 37 条
  • [1] Chen L., 2023, Coal Eng, V55, P13
  • [2] A Case Study of Optimization and Application of Soft-Rock Roadway Support in Xiaokang Coal Mine, China
    Guo, Shuai
    Zhu, Xun-Guo
    Liu, Xun
    Duan, Hong-Fei
    [J]. ADVANCES IN CIVIL ENGINEERING, 2021, 2021
  • [3] Numerical Simulation on Pillar Design for Longwall Mining under Weak Immediate Roof and Floor Strata in Indonesia
    Hashikawa, Hiroto
    Mao, Pisith
    Sasaoka, Takashi
    Hamanaka, Akihiro
    Shimada, Hideki
    Batsaikhan, Ulaankhuu
    Oya, Jiro
    [J]. SUSTAINABILITY, 2022, 14 (24)
  • [4] He M., 2017, Coal Sci. Technol, V1, P1, DOI DOI 10.19896/J.CNKI.MTKJ.2017.01.002
  • [5] Analysis of Strata Behavior Process Characteristics of Gob-Side Entry Retaining with Roof Cutting and Pressure Releasing Based on Composite Roof Structure
    He, Manchao
    Ma, Xingen
    Yu, Bin
    [J]. SHOCK AND VIBRATION, 2019, 2019
  • [6] [何满潮 He Manchao], 2018, [煤炭学报, Journal of China Coal Society], V43, P626
  • [7] [何满潮 He Manchao], 2017, [中国矿业大学学报. 自然科学版, Journal of China University of Mining & Technology], V46, P959
  • [8] Field and simulation study of the rational coal pillar width in extra-thick coal seams
    He, Wenrui
    He, Fulian
    Zhao, Yongqiang
    [J]. ENERGY SCIENCE & ENGINEERING, 2020, 8 (03) : 627 - 646
  • [9] Jia S., 2011, ISMSSE, P26, DOI [10.1016/j.proeng.2011.11.2282, DOI 10.1016/J.PROENG.2011.11.2282]
  • [10] Failure Characteristics of the Water-Resisting Coal Pillar under Stress-Seepage Coupling and Determination of Reasonable Coal Pillar Width
    Liu, Quanhui
    Xue, Yuanbo
    Ma, Dan
    Li, Qiang
    [J]. WATER, 2023, 15 (05)