Exploring the critical production risk factors for modular integrated construction projects

被引:11
作者
Wuni, Ibrahim Yahaya [1 ]
Shen, Geoffrey Qiping [1 ]
机构
[1] Hong Kong Polytech Univ, Dept Bldg & Real Estate, Hung Hom, Kowloon, Hong Kong, Peoples R China
关键词
Modular integrated construction; Production risks; Risk factors; Supply chain; Severity; Risk management; OFF-SITE CONSTRUCTION; PERFORMANCE; IMPLEMENTATION; OPPORTUNITIES; COORDINATION; BUILDINGS; SYSTEM;
D O I
10.1108/JFM-03-2021-0029
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
Purpose The factory production stage constitutes the bridge in the supply chains of modular integrated construction (MiC) projects. It embodies the fundamental differences between MiC and site-based construction. However, there is a poverty of knowledge of the uncertainties and risk events at the production stage. This study aims to investigate the critical production risk factors (PRFs) for MiC projects. Design/methodology/approach Comprehensive literature research and expert review identified and validated 22 candidate PRFs for MiC projects. A structured questionnaire survey was then used to gather opinions of domain experts in 18 countries on the relative impact of the validated PRFs for MiC projects. The collected data were analysed using multiple statistical techniques. Findings Statistical analysis identified nine critical PRFs for MiC projects. The top five include dimensional conflicts between modules during production; delays in production materials procurement; defective design; design information gap between designer and manufacturer; and limited capacity of manufacturers. Originality/value The study addressed the gap associated with identifying critical risk factors peculiar to the factory production stage of MiC projects. Its novelty lies in providing an opposite assessment of severities and prioritization of critical PRFs for MiC projects. The prioritized critical PRFs for MiC projects may inform resource allocation. Thus, it provides valuable information to MiC production specialists and project managers in their production risk planning and management strategies. The identified PRFs contribute to the theoretical checklist of MiC supply chain risk factors and may assist practitioners in assessing the severity levels of the PRFs of their MiC projects.
引用
收藏
页码:50 / 68
页数:19
相关论文
共 52 条
  • [1] Evaluation and ranking of risk factors in public-private partnership water supply projects in developing countries using fuzzy synthetic evaluation approach
    Ameyaw, Effah Ernest
    Chan, Albert P. C.
    [J]. EXPERT SYSTEMS WITH APPLICATIONS, 2015, 42 (12) : 5102 - 5116
  • [2] [Anonymous], 2016, INTRO STAT METHODS D
  • [3] [Anonymous], 2017, A guide to the project management body of knowledge: PMBOK guide
  • [4] Becker JMJ., 2013, SMART PRODUCT ENG, P33
  • [5] Blismas N., 2007, Off-site manufacture in Australia: Current state and future directions
  • [6] Benefit evaluation for off-site production in construction
    Blismas, Nick
    Pasquire, Christine
    Gibb, Alistair
    [J]. CONSTRUCTION MANAGEMENT AND ECONOMICS, 2006, 24 (02) : 121 - 130
  • [7] PRODUCT DESIGN FOR MANUFACTURE AND ASSEMBLY
    BOOTHROYD, G
    [J]. COMPUTER-AIDED DESIGN, 1994, 26 (07) : 505 - 520
  • [8] Building and Construction Authority, 2017, OV DES MAN ASS DFMA
  • [9] Chou YM, 1998, J QUAL TECHNOL, V30, P133
  • [10] Supply-chain transparency within industrialized construction projects
    Cus-Babic, Nenad
    Rebolj, Danijel
    Nekrep-Perc, Matjaz
    Podbreznik, Peter
    [J]. COMPUTERS IN INDUSTRY, 2014, 65 (02) : 345 - 353