Weighted Multi-Skill Resource Constrained Project Scheduling: A Greedy and Parallel Scheduling Approach

被引:3
作者
Akbar, Saeed [1 ]
Zubair, Muhammad [2 ]
Khan, Rizwan [1 ]
Ul Akbar, Ubaid [3 ]
Ullah, Rahmat [4 ]
Zheng, Zhonglong [1 ]
机构
[1] Zhejiang Normal Univ, Sch Comp Sci & Technol, Jinhua 321004, Peoples R China
[2] Lahore Garrison Univ, Dept Software Engn, Lahore 54000, Pakistan
[3] City Univ Sci & Informat Technol, Dept Comp Sci, Peshawar 44050, Pakistan
[4] Univ Essex, Sch Comp Sci & Elect Engn, Colchester CO4 3SQ, England
关键词
Task analysis; Global Positioning System; Job shop scheduling; Costs; Resource management; Software; Project management; Greedy and parallel scheduling; heterogeneous skill proficiency; parallel scheduling scheme; project scheduling; resource assignment; weighted multi-skilled resources; ALGORITHM;
D O I
10.1109/ACCESS.2024.3350440
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
This study addresses the Weighted Multi-Skill Resource Constrained Project Scheduling Problem (W-MSRCSPSP) with the aim of minimizing software project makespan. Unlike previous works, our investigation regards heterogeneous resources characterized by varying skill proficiency levels. Another major problem with existing methodologies is the potential underutilization of human resources due to varying task durations. This work introduces an innovative scheduling approach known as the Greedy and Parallel Scheduling (GPS) algorithm to handle the said issues. GPS focuses on assigning the most suitable resources available to project activities at each scheduling point. The fundamental goal of our proposed approach is to reduce resource wastage while efficiently allocating surplus resources, if any, to project tasks, ultimately leading to a decrease in the makespan. To empirically evaluate the efficacy of the GPS algorithm, we conduct a comparative analysis against the Parallel Scheduling Scheme (PSS). The advantage of our proposed approach lies in its ability to optimize the utilization of available resources, resulting in accelerated project completion. Results from extensive simulations substantiate this claim, demonstrating that the GPS scheme outperforms the PSS approach in minimizing project duration.
引用
收藏
页码:29824 / 29836
页数:13
相关论文
共 50 条
  • [41] An approach with Decomposition on Time Windows for Resource-Constrained Project Scheduling
    Tian, Jing
    Liu, Zhenyuan
    Yu, Wenmin
    26TH CHINESE CONTROL AND DECISION CONFERENCE (2014 CCDC), 2014, : 4897 - 4903
  • [42] Multi-mode resource constrained multi-project scheduling and resource portfolio problem
    Besikci, Umut
    Bilge, Umit
    Ulusoy, Gunduz
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2015, 240 (01) : 22 - 31
  • [43] A lexicographic approach to the robust resource-constrained project scheduling problem
    Palacio, Juan D.
    Larrea, Olga L.
    INTERNATIONAL TRANSACTIONS IN OPERATIONAL RESEARCH, 2017, 24 (1-2) : 143 - 157
  • [44] A Resource Constrained Project Scheduling Problem With Multi-Modes
    Altintas, Cansu
    Azizoglu, Meral
    INTERNATIONAL JOURNAL OF INFORMATION TECHNOLOGY PROJECT MANAGEMENT, 2020, 11 (01) : 55 - 70
  • [45] Genetic Algorithm for Singular Resource Constrained Project Scheduling Problems
    Mahmud, Firoz
    Zaman, Forhad
    Ahrari, Ali
    Sarker, Ruhul
    Essam, Daryl
    IEEE ACCESS, 2021, 9 : 131767 - 131779
  • [46] Optimal Dynamic Resource Allocation for the Multi-mode Resource Constrained Project Scheduling via Non-Greedy Heuristic and Adaptive Metaheuristic
    Liu Xun
    Zhang Yi
    Li Hui-Ming
    PROCEEDINGS OF 2009 INTERNATIONAL CONFERENCE OF MANAGEMENT SCIENCE AND INFORMATION SYSTEM, VOLS 1-4, 2009, : 319 - 324
  • [47] An integrated solution approach for multi-objective, multi-skill workforce scheduling and routing problems
    Cakirgil, Seray
    Yucel, Eda
    Kuyzu, Gultekin
    COMPUTERS & OPERATIONS RESEARCH, 2020, 118
  • [48] A Tabu Search Approach for the Resource Constrained Project Scheduling Problem
    Paul R. Thomas
    Said Salhi
    Journal of Heuristics, 1998, 4 : 123 - 139
  • [49] A Neurogenetic approach for the resource-constrained project scheduling problem
    Agarwal, Anurag
    Colak, Selcuk
    Erenguc, Selcuk
    COMPUTERS & OPERATIONS RESEARCH, 2011, 38 (01) : 44 - 50
  • [50] A tabu search approach for the resource constrained project scheduling problem
    Thomas, PR
    Salhi, S
    JOURNAL OF HEURISTICS, 1998, 4 (02) : 123 - 139