Hierarchical structure and transfer mechanism to assess the scheduling-related risk in construction of prefabricated buildings: an integrated ISM-MICMAC approach

被引:20
作者
Fan, Cheng [1 ]
Deng Binchao [2 ]
Yin, Yilin [1 ]
机构
[1] Tianjin Univ Technol, Tianjin, Peoples R China
[2] Tianjin Univ Technol, Sch Management, Tianjin, Peoples R China
关键词
Prefabricated buildings; Scheduling risk in construction; Interpretive structural model; MICMAC analysis; General contractor; OFF-SITE CONSTRUCTION; SUPPLY CHAIN; ON-SITE; PROJECTS; MANAGEMENT; CHINA; PERFORMANCE; BARRIERS; TRANSPORTATION; IDENTIFICATION;
D O I
10.1108/ECAM-09-2021-0785
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Purpose Under the background that engineering, procurement and construction (EPC) contracting model is introduced to adapt to the highly fragmented characteristics of prefabricated construction, the schedule management of general contractor is faced with the challenge of dynamic transmission and interaction of construction scheduling-related risk. The purpose of this paper is to develop the hierarchy of prefabricated construction scheduling-related risks from the perspective of the general contractor, and to analyze the transmission mechanism between risks. The paper also aims to further distinguish the difference of the impact degree of scheduling-related risks, and provide reference for formulating the strategy to alleviate the construction delay. Design/methodology/approach Based on a review of the literature on prefabricated buildings, this paper identifies 22 scheduling-related risks in construction from the perspective of the general contractor. Semi-structured interviews were then conducted to obtain experts' views on the interrelationships among these risks. Following this, their overall structure was determined by using a hierarchical structure established by using interpretive structural modeling (ISM), and Matrice d'Impacts Croises Multiplication Appliques a un Classement (MICMAC) technique was applied to classify them into four groups according to their driving and dependence powers. Findings The results indicate that the 22 scheduling-related risks in construction followed the inherent path of step-by-step transmission, and all of them could cause different degrees of delays in prefabricated construction. Among them, general experience in contracting projects, the use of emerging technologies and the completeness of the relevant standards and specifications were strong drivers of scheduling delays in construction, and should be prioritized by the general contractor in schedule management. The transitive link between scheduling risks can guide them in developing prevention strategies. Research limitations/implications Data quality and reliability risks are the major drawbacks of semi-structured interviews. These were minimized by engaging experts with rich theoretical and hands-on experience in prefabricated construction projects. The hierarchical model only reflects static influence relationships, and so dynamic interactions among scheduling-related risks should be studied in future. Originality/value The primary value of this study is in its development of a hierarchical model by using the integrated ISM-MICMAC approach that reflects the interaction between scheduling risks in the construction of prefabricated buildings. The hierarchy of these risks and the results of a "driving-dependence power" analysis can guide the general contractor in taking targeted preventive measures to avoid scheduling delays in the construction of prefabricated buildings.
引用
收藏
页码:2991 / 3013
页数:23
相关论文
共 68 条
[1]  
Adel M.B., 2016, INT J ADV SCI RES MA, V1, P51
[2]   Supply chain risk factors in green construction of residential mega projects - interactions and categorization [J].
Alamdari, Ardalan Marandi ;
Jabarzadeh, Younis ;
Samson, Daniel ;
Sanoubar, Naser .
ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2023, 30 (02) :568-597
[3]   A multi-objective GA-based optimisation for holistic Manufacturing, transportation and Assembly of precast construction [J].
Anvari, B. ;
Angeloudis, P. ;
Ochieng, W. Y. .
AUTOMATION IN CONSTRUCTION, 2016, 71 :226-241
[4]   Performance-based control of variability and tolerance in off-site manufacture and assembly: optimization of penalty on poor production quality [J].
Arashpour, Mehrdad ;
Heidarpour, Amin ;
Nezhad, Ali ;
Hosseinifard, Zahra ;
Chileshe, Nicholas ;
Hosseini, Reza .
CONSTRUCTION MANAGEMENT AND ECONOMICS, 2020, 38 (06) :502-514
[5]   Analysis of interacting uncertainties in on-site and off-site activities: Implications for hybrid construction [J].
Arashpour, Mehrdad ;
Wakefield, Ron ;
Lee, E. W. M. ;
Chan, Ricky ;
Hosseini, M. Reza .
INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2016, 34 (07) :1393-1402
[6]  
Arditi D., 2000, J ARCHITECTURAL ENG, V6, P79, DOI DOI 10.1061/(ASCE)1076-0431(2000)6:3(79)
[7]  
Attri R., 2013, RES J MANAGEMENT SCI, V2, P3
[8]   Factors Affecting the Design, Manufacturing, Storage, Transportation, and Construction Processes of Prefabricated Buildings [J].
Ay, Ilhami ;
Ayalp, Gulden Gumusburun .
TEKNIK DERGI, 2021, 32 (03) :10907-10917
[9]  
Blismas Nick, 2009, Construction Innovation, V9, P72, DOI 10.1108/14714170910931552
[10]   Unlocking the green opportunity for prefabricated buildings and construction in China [J].
Chang, Yuan ;
Li, Xiaodong ;
Masanet, Eric ;
Zhang, Lixiao ;
Huang, Zhiye ;
Ries, Robert .
RESOURCES CONSERVATION AND RECYCLING, 2018, 139 :259-261