Critical chain based Proactive-Reactive scheduling for Resource-Constrained project scheduling under uncertainty

被引:19
|
作者
Peng, Wuliang [1 ]
Lin, Xuejun [1 ]
Li, Haitao [2 ]
机构
[1] Yantai Univ, Sch Econ & Management, Yantai, Peoples R China
[2] Univ Missouri St Louis, Coll Business Adm, St Louis, MO USA
基金
中国国家自然科学基金;
关键词
Stochastic resource-constrained project scheduling; Critical chain method; Proactive-reactive scheduling; Approximate dynamic programming; Look-up table; BUFFER MANAGEMENT;
D O I
10.1016/j.eswa.2022.119188
中图分类号
TP18 [人工智能理论];
学科分类号
081104 ; 0812 ; 0835 ; 1405 ;
摘要
Project scheduling problems under both resource constraints and uncertainty have been widely studied due to their real world relevance. In this paper, we design and implement a new integrated proactive-reactive solution approach based on the critical chain method (CCM) to proactively generate a robust and reliable baseline schedule for the class of resource-constrained project scheduling problem (RCPSP) under uncertainty. A discretetime Markov decision process model is applied for the reactive scheduling phase, which embeds the look-up table method in reinforcement learning to dynamically schedule and adjust schedule reactively using the baseline schedule during project execution. The cost values in the look-up table are calculated based on the occupation of a project buffer and feeding buffers in the baseline schedule generated by the CCM. We conduct computation experiments on the benchmark instances to test our algorithm. The results show that our approach is able to obtain quality solutions efficiently, and competitive with the benchmark algorithms for small- and medium-sized instances.
引用
收藏
页数:12
相关论文
共 50 条
  • [1] The proactive and reactive resource-constrained project scheduling problem
    Morteza Davari
    Erik Demeulemeester
    Journal of Scheduling, 2019, 22 : 211 - 237
  • [2] The proactive and reactive resource-constrained project scheduling problem
    Davari, Morteza
    Demeulemeester, Erik
    JOURNAL OF SCHEDULING, 2019, 22 (02) : 211 - 237
  • [3] Proactive and reactive strategies for resource-constrained project scheduling with uncertain resource availabilities
    Lambrechts, Olivier
    Demeulemeester, Erik
    Herroelen, Willy
    JOURNAL OF SCHEDULING, 2008, 11 (02) : 121 - 136
  • [4] Proactive and reactive strategies for resource-constrained project scheduling with uncertain resource availabilities
    Olivier Lambrechts
    Erik Demeulemeester
    Willy Herroelen
    Journal of Scheduling, 2008, 11 : 121 - 136
  • [5] Important classes of reactions for the proactive and reactive resource-constrained project scheduling problem
    Davari, Morteza
    Demeulemeester, Erik
    ANNALS OF OPERATIONS RESEARCH, 2019, 274 (1-2) : 187 - 210
  • [6] Important classes of reactions for the proactive and reactive resource-constrained project scheduling problem
    Morteza Davari
    Erik Demeulemeester
    Annals of Operations Research, 2019, 274 : 187 - 210
  • [7] Coordination-based reactive resource-constrained project scheduling
    Joo, Byung Jun
    Chua, Tay Jin
    Cai, Tian Xiang
    Chua, Ping Chong
    52ND CIRP CONFERENCE ON MANUFACTURING SYSTEMS (CMS), 2019, 81 : 51 - 56
  • [8] The Proactive Resource-Constrained Project Scheduling Problem with Resource Transfer Times
    Ma, Zhiqiang
    He, Zhengwen
    Wang, Nengmin
    PROCEEDINGS OF THE 2019 INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND SYSTEMS MANAGEMENT (IESM 2019), 2019, : 642 - 647
  • [9] Proactive policies for the stochastic resource-constrained project scheduling problem
    Deblaere, Filip
    Demeulemeester, Erik
    Herroelen, Willy
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2011, 214 (02) : 308 - 316
  • [10] A reactive scheduling approach for the resource-constrained project scheduling problem with dynamic resource disruption
    Xu, Jiaojiao
    Bai, Sijun
    KYBERNETES, 2024, 53 (06) : 2007 - 2028