Causes, Effects, and Mitigation Measures of Time and Cost Overruns in Water Supply Projects: Case of Tigrai Region, Northern Ethiopia

被引:0
作者
Berihu, Lielti Gebreegziabher [1 ]
Grum, Berhane [1 ]
Tariku, Zeru [1 ]
Abebe, Bizuneh Asfaw [1 ]
机构
[1] Mekelle Univ, Ethiopian Inst Technol Mekelle, Sch Civil Engn, POB 231, Mekelle, Ethiopia
关键词
CONSTRUCTION; DELAY;
D O I
10.1155/2023/7113730
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Project cost overrun and schedule delay are major and widespread problems in the construction industry. In Tigrai, most water supply construction projects are not completed within the predetermined contract time and planned budget. Hence, this research was carried out to investigate the causes and effects of time and cost overrun in water supply projects in Tigrai, northern Ethiopia and further recommend effective mitigation measures. A total of 87 questionnaires were distributed, 50 of them were collected, and desk study of 12 water supply projects were conducted. Data were analyzed using relative importance index and statistical software SPSS version 20. Results showed that the most important causes of time overrun were design errors and changes, lack of consistency between bill of quantities and drawings, and change order. Similarly, the most important causes of cost overrun were design errors and changes, lack of consistency between bill of quantities and drawings, and shortage of construction materials and electromechanical equipment in local market. The most effective mitigation measure of the overruns was complete and proper design. Time and cost overrun of the projects ranged between 0 and 203% and between 0 and 25%, respectively. The regression model showed that time overrun was estimated well (r(2) = 0.95) using delays caused by design errors and changes and material import. Similarly, cost overrun was estimated well (r(2) = 0.98) using factors that affect cost. Overall, the major cause for the overruns was design problem, hence clients and consultants should give due attention for the design process.
引用
收藏
页数:19
相关论文
共 36 条
  • [1] Urban Infrastructure Development Works in India: Delay and Difficulties in Implementation with Reference to a Water Supply Project
    Aditya A.K.
    Douglass D.A.
    Bhattacharya M.
    [J]. Journal of The Institution of Engineers (India): Series A, 2017, 98 (03) : 349 - 354
  • [2] The significant factors causing delay of building construction projects in Malaysia
    Alaghbari, Wa'el
    Kadir, Mohd. Razali A.
    Salim, Azizah
    Ernawati
    [J]. ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2007, 14 (02) : 192 - +
  • [3] Alamri N., 2017, European Journal of Business and Social Sciences, V6, P19
  • [4] [Anonymous], 2015, THESIS ADDIS ABABA U
  • [5] Should we build more large dams? The actual costs of hydropower megaproject development
    Ansar, Atif
    Flyvbjerg, Bent
    Budzier, Alexander
    Lunn, Daniel
    [J]. ENERGY POLICY, 2014, 69 : 43 - 56
  • [6] Causes of delay in large construction projects
    Construction Engineering and Management Department, King Fahd University of Petroleum and Minerals, Box # 680, Dhahran, 31261, Saudi Arabia
    [J]. Int. J. Proj. Manage., 2006, 4 (349-357): : 349 - 357
  • [7] Ayenew A., 2011, BASELINE SURVEY REPO
  • [8] Azhar N.F., 2008, P 1 INT C CONSTRUCTI
  • [9] Factors causing cost variation for constructing wastewater projects in Egypt
    Aziz, Remon Fayek
    [J]. ALEXANDRIA ENGINEERING JOURNAL, 2013, 52 (01) : 51 - 66
  • [10] Bhagat S. A., 2017, INT J RECENT INNOVAT, V5, P241