Incorporation price uncertainty into open-pit to underground mine transition

被引:5
|
作者
Dehghani, Hesam [1 ]
Sakinezhad, Reza [1 ]
Nabavi, Zohre [2 ]
Babanouri, Nima [1 ]
机构
[1] Hamedan Univ Technol, Fac Min Engn, Hamadan, Iran
[2] Tarbiat Modares Univ, Fac Engn, Dept Min Engn, Tehran, Iran
关键词
Transition depth; Price uncertainty; Monte Carlo simulation; Open-pit mining; Underground mining; OPTIMIZATION; DEPTH;
D O I
10.1007/s13563-023-00408-9
中图分类号
F [经济];
学科分类号
02 ;
摘要
The growing demand for primary mineral resources and the finite nature of mineral reserves necessitate their efficient utilization while minimizing losses. To extend mine life and increase economic reserves, transitioning from open-pit to underground mining has proven to be a viable strategy. Identifying this critical transition depth is pivotal, as it significantly impacts mining profitability. Therefore, in this paper we propose a method to determine the open-pit/underground transition depth based on an economic block model, accounting for the final pit limit and considering the inherent uncertainty in mineral prices. To achieve our research aim, a hypothetical grade model was constructed initially, and we used @Risk software to perform Monte Carlo simulation of copper prices based on historical data. By generating 200 different mineral price scenarios, we created 200 economic block models. Subsequently, nine mining sequences were designed, and seven distinct scenarios were established to ascertain the final open-pit limit and the depth of the transition point between mining methods, contingent on fluctuating mineral prices. Based on the outcomes derived from the seven scenarios, the depth at which the mining method transition from open-pit to underground is recommended to be 375 m from the surface, under the aforementioned uncertainties. This recommendation is based on the cumulative net present value of open-pit/underground mining, as illustrated in scenario number 7. Our findings provide valuable insights for mining companies seeking to optimize resource utilization and maximize profitability while navigating uncertain mineral price environments.
引用
收藏
页码:89 / 99
页数:11
相关论文
共 50 条
  • [41] Optimizing the open pit-to-underground mining transition
    King, Barry
    Goycoolea, Marcos
    Newman, A.
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2017, 257 (01) : 297 - 309
  • [42] A Mine-to-Crusher Model to Minimize Costs at a Truckless Open-Pit Iron Mine in Brazil
    Navarro Torres, Vidal Felix
    Figueiredo, Janine Rodrigues
    De La Hoz, Raul Carretero
    Botaro, Marcio
    Chaves, Leonardo Soares
    MINERALS, 2022, 12 (08)
  • [43] Analysis of deformation mechanism of soft rock composite slope in open-pit mine
    Li M.
    Qiao L.
    Tian Y.
    Du H.
    Meitan Kexue Jishu/Coal Science and Technology (Peking), 2021, 49 (08): : 108 - 113
  • [44] A real-world mine excavators timetabling methodology in open-pit mining
    Liu, Shi Qiang
    Kozan, Erhan
    Corry, Paul
    Masoud, Mahmoud
    Luo, Kai
    OPTIMIZATION AND ENGINEERING, 2023, 24 (03) : 1493 - 1535
  • [45] Geotechnical study for optimizing the slope design of a deep open-pit mine, India
    Singh, VK
    Singh, JK
    Kumar, A
    BULLETIN OF ENGINEERING GEOLOGY AND THE ENVIRONMENT, 2005, 64 (03) : 303 - 309
  • [46] Stability Analysis and Optimized Slope Angle for the Iron Ore Open-Pit Mine
    Akdag, S.
    Basarir, H.
    Karpuz, C.
    Ozyurt, M.
    PROCEEDINGS OF THE 24TH INTERNATIONAL MINING CONGRESS AND EXHIBITION OF TURKEY, IMCET 2015, 2015, : 606 - 611
  • [47] An integrated model of an open-pit coal mine: improving energy efficiency decisions
    Patterson, S. R.
    Kozan, E.
    Hyland, P.
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2016, 54 (14) : 4213 - 4227
  • [48] Numerical Simulation Research on the Influence of Tailings Surcharge Load at Open-pit Mine
    Zhou Chunmei
    Zhang Dianji
    SPORTS, ARTS MATERIALS AND MANAGEMENT SCIENCE, 2012, 507 : 237 - +
  • [49] Model studies of an open-pit mine bottom loaded by artesian water pressure
    Trckova, J
    ENVIRONMENTAL GEOLOGY, 1998, 35 (04): : 245 - 250
  • [50] Dangerous and harmful factors in the process of open-pit mine production and prevention countermeasures
    Jia, Qingmei
    Wang, Weizhi
    Li, Ying
    MATERIALS PROCESSING AND MANUFACTURING III, PTS 1-4, 2013, 753-755 : 3162 - 3165