RESOURCE LEVELLING IN REPETITIVE CONSTRUCTION PROJECTS WITH INTERRUPTIONS: AN INTEGRATED APPROACH

被引:10
作者
Dai, Guyu [1 ]
Liao, Mingjuan [1 ]
Zhang, Renqian [1 ]
机构
[1] Beihang Univ, Sch Econ & Management, Beijing, Peoples R China
基金
中国国家自然科学基金;
关键词
construction management; repetitive construction project; scheduling; resource levelling; work interruption; optimization; DIFFERENT OBJECTIVE FUNCTIONS; COST OPTIMIZATION; SCHEDULING METHOD; MODEL; IMPACTS; BALANCE; LINE;
D O I
10.3846/jcem.2023.17568
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Despite the significance of resource levelling, project managers lack various ways to smooth resource usage fluc-tuation of a repetitive construction project besides changing resource usage. Tolerating interruptions is an effective way to provide flexibility for a schedule but is ignored when solving resource levelling problems. Therefore, this paper investigates the impacts of interruptions on resource usage fluctuation and develops an integrated approach that simultaneously inte-grates two scheduling adjusting processes: changing resource usage and tolerating interruptions. In this paper, two inter-ruption conditions are proposed to identify which activities are suitable to be interrupted for smoothing resource usage fluctuation. The traditional resource levelling model is modified to a new scheduling model by incorporating interruptions. A two-stage GA-based scheduling algorithm is developed by integrating changing resource usage and tolerating interrup-tions. A commonly used pipeline project is adopted to illustrate the steps of the proposed approach and demonstrate its effectiveness and superiority through comparison with previous studies. A large-scale project further verifies the usability of the proposed approach. The results confirmed the feasibility to smooth resource usage fluctuation by interruptions, and the integrated approach can achieve a more competitive resource levelling result.
引用
收藏
页码:93 / 106
页数:14
相关论文
共 43 条
[1]   Multi-objective genetic optimization for scheduling a multi-storey building [J].
Agrama, Fatma A. .
AUTOMATION IN CONSTRUCTION, 2014, 44 :119-128
[2]   Optimizing the Scheduling of Repetitive Construction to Minimize Interruption Cost [J].
Altuwaim, Ayman ;
El-Rayes, Khaled .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2018, 144 (07)
[3]   Minimizing duration and crew work interruptions of repetitive construction projects [J].
Altuwaim, Ayman ;
El-Rayes, Khaled .
AUTOMATION IN CONSTRUCTION, 2018, 88 :59-72
[4]  
Amini S. M., 2009, AACE INT T, V4, P1
[5]   Optimization of line of balance scheduling considering work interruption [J].
Ammar, Mohammad A. .
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2019, :305-316
[6]   Resource optimisation in line of balance scheduling [J].
Ammar, Mohammad A. .
CONSTRUCTION MANAGEMENT AND ECONOMICS, 2020, 38 (08) :715-725
[7]   LOB and CPM Integrated Method for Scheduling Repetitive Projects [J].
Ammar, Mohammad A. .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2013, 139 (01) :44-50
[8]  
Arditi D., 2001, Engineering, Construction and Architectural Management, V8, P90, DOI DOI 10.1046/J.1365-232X.2001.00186.X
[9]  
Bragadin M., 2010, TG65 W065 SPECIAL TR, P331
[10]   FUZZY CLUSTERING CHAOTIC-BASED DIFFERENTIAL EVOLUTION FOR RESOURCE LEVELING IN CONSTRUCTION PROJECTS [J].
Cheng, Min-Yuan ;
Tran, Duc-Hoc ;
Hoang, Nhat-Duc .
JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2017, 23 (01) :113-124