Solution of discrete time-cost trade-off problem with adaptive search domain

被引:4
|
作者
Bettemir, Onder Halis [1 ]
Birgonul, M. Talat [2 ]
机构
[1] Inonu Univ, Dept Civil Engn, Malatya, Turkiye
[2] Middle East Tech Univ, Dept Civil Engn, Ankara, Turkiye
关键词
Project scheduling; Differential evolution; Meta-heuristic algorithm; Time-cost trade-off problem; Optimization; Ultraploidy; CONSTRUCTION TIME; GENETIC ALGORITHM; DIFFERENTIAL EVOLUTION; OPTIMIZATION; MODEL; COMPRESSION;
D O I
10.1108/ECAM-06-2022-0601
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
PurposeExact solution of time-cost trade-off problem (TCTP) by the state-of-the-art meta-heuristic algorithms can be obtained for small- and medium-scale problems, while satisfactory results cannot be obtained for large construction projects. In this study, a hybrid heuristic meta-heuristic algorithm that adapts the search domain is developed to solve the large-scale discrete TCTP more efficiently.Design/methodology/approachMinimum cost slope-based heuristic network analysis algorithm (NAA), which eliminates the unfeasible search domain, is embedded into differential evolution meta-heuristic algorithm. Heuristic NAA narrows the search domain at the initial phase of the optimization. Moreover, activities with float durations higher than the predetermined threshold value are eliminated and then the meta-heuristic algorithm starts and searches the global optimum through the narrowed search space. However, narrowing the search space may increase the probability of obtaining a local optimum. Therefore, adaptive search domain approach is employed to make reintroduction of the eliminated activities to the design variable set possible, which reduces the possibility of converging into local minima.FindingsThe developed algorithm is compared with plain meta-heuristic algorithm with two separate analyses. In the first analysis, both algorithms have the same computational demand, and in the latter analysis, the meta-heuristic algorithm has fivefold computational demand. The tests on case study problems reveal that the developed algorithm presents lower total project costs according to the dependent t-test for paired samples with alpha = 0.0005.Research limitations/implicationsIn this study, TCTP is solved without considering quality or restrictions on the resources.Originality/valueThe proposed method enables to adapt the number of parameters, that is, the search domain and provides the opportunity of obtaining significant improvements on the meta-heuristic algorithms for other engineering optimization problems, which is the theoretical contribution of this study. The proposed approach reduces the total construction cost of the large-scale projects, which can be the practical benefit of this study.
引用
收藏
页码:1032 / 1052
页数:21
相关论文
共 50 条
  • [41] Time-Cost Trade-off Problems of Engineering Project with Running Income
    Li, Hongxian
    Ouyang, Hongxiang
    2008 INTERNATIONAL CONFERENCE ON RISK MANAGEMENT AND ENGINEERING MANAGEMENT, ICRMEM 2008, PROCEEDINGS, 2008, : 9 - +
  • [42] Modeling project time-cost trade-off in fuzzy random environment
    Ke, Hua
    Ma, Junjie
    APPLIED SOFT COMPUTING, 2014, 19 : 80 - 85
  • [43] CBO and CSS Algorithms for Resource Allocation and Time-Cost Trade-Off
    Kaveh, Ali
    Khanzadi, Mostafa
    Alipour, Majid
    Naraky, Mohammad Rajabi
    PERIODICA POLYTECHNICA-CIVIL ENGINEERING, 2015, 59 (03): : 361 - 371
  • [44] Automated BIM schedule generation approach for solving time-cost trade-off problems
    ElMenshawy, Mohamed
    Marzouk, Mohamed
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2021, 28 (10) : 3346 - 3367
  • [45] Time-cost trade-off optimization with a new initial population approach
    Toğan V.
    Eirgash M.A.
    Teknik Dergi/Technical Journal of Turkish Chamber of Civil Engineers, 2019, 30 (06): : 9561 - 9580
  • [46] A new approach to solve time-cost trade-off problem with fuzzy decision variables
    Ghazanfari, M.
    Yousefli, A.
    Ameli, M. S. Jabal
    Bozorgi-Amiri, A.
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2009, 42 (3-4) : 408 - 414
  • [47] Multiproject Time-cost Trade-off Scheduling Problem for Large-scale Construction Systems under Fuzzy Uncertainty
    Ouyang Yong-liu
    Zhang Meng-xiang
    Han Lu
    Lu Yi
    2015 INTERNATIONAL CONFERENCE ON MANAGEMENT SCIENCE & ENGINEERING - 22ND ANNUAL CONFERENCE PROCEEDINGS, VOLS I AND II, 2015, : 282 - 292
  • [48] The discrete time/cost trade-off problem: extensions and heuristic procedures
    Vanhoucke, Mario
    Debels, Dieter
    JOURNAL OF SCHEDULING, 2007, 10 (4-5) : 311 - 326
  • [49] The discrete time/cost trade-off problem: extensions and heuristic procedures
    Mario Vanhoucke
    Dieter Debels
    Journal of Scheduling, 2007, 10 : 311 - 326
  • [50] Robust optimization models for the discrete time/cost trade-off problem
    Hazir, Oncu
    Erel, Erdal
    Gunalay, Yavuz
    INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2011, 130 (01) : 87 - 95