Performance Comparison of Break and Seat and Rubblization Rehabilitation Techniques for Reflection-Crack Mitigation: Case Study in Louisiana

被引:5
作者
Akentuna, Moses [1 ]
Chen, Qiming [1 ]
Zhang, Zhongjie [1 ]
机构
[1] Louisiana Transportat Res Ctr, Louisiana Dept Transportat & Dev, Baton Rouge, LA 70808 USA
关键词
reflection-crack mitigation; rubblization; break and seat; pavement condition index; asphalt overlay; falling weight deflectometer;
D O I
10.1177/03611981221150398
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Hot mix asphalt (HMA) overlays are constructed on Portland cement concrete (PCC) pavements to improve long-term performance. A significant disadvantage of using HMA overlays on PCC pavements is the development of reflection cracks. Reflection cracks are influenced by traffic loads and periodic temperature changes. The objective of the study was to compare field performance of two slab-fracturing (i.e., break and seat, and rubblization) techniques commonly used in Louisiana, U.S. Four PCC pavement rehabilitation projects with at least one slab-fracturing technique and a corresponding control section were evaluated. Field structural capacity and performance data were collected and analyzed to determine the effect of each reflection-crack mitigation technique on performance. Resilient modulus (M-r) of the existing subgrade was found to significantly influence the structural and functional performance of the pavement sections evaluated. Pavement sections with weaker subgrades were shown to be not suitable for slab-fracturing rehabilitation techniques. For the four field projects evaluated, rubblized test sections showed higher cracking resistance than the control sections. The break and seat technique did not consistently improve or reduce the crack resistance of pavement sections compared with their corresponding control sections because of variations in subgrade M-r values. Sections with smaller sized (i.e., 6 in. break pattern and rubblized particles) fractured particles exhibited higher cracking resistance. Rubblized and selected break and seat sections for the field projects evaluated exhibited lower overall performance compared with their corresponding control sections, which is attributed to other underlying subsurface conditions. Additional study is required to continuously monitor the pavement sections.
引用
收藏
页码:837 / 851
页数:15
相关论文
共 34 条
[1]  
AASHTO, 1993, Guide for Design of Pavement Structures
[2]  
Arhin S. A., 2012, WIT T BUILT ENV, V128, P527
[3]  
Baladi G., 2017, Pavement Performance Measures and Forecasting and the Effects of Maintenance and Rehabilitation Strategy on Treatment Effectiveness
[4]  
Beg MA, 2000, TRANSPORT RES REC, P23
[5]   Field and Laboratory Forensic Analysis of Reflective Cracking on Massachusetts Interstate 495 [J].
Bennert, Thomas ;
Worden, Michael ;
Turo, Matthew .
TRANSPORTATION RESEARCH RECORD, 2009, (2126) :27-38
[6]  
Ceylan H., 2005, TR473 IHRB IOW STAT
[7]   Implementation of Network-Level Falling Weight Deflectometer Survey [J].
Chowdhury, Tanveer ;
Shekharan, Raja A. ;
Diefenderfer, Brian K. .
TRANSPORTATION RESEARCH RECORD, 2012, (2304) :3-9
[8]  
Decker D.S., 2006, Design and Construction of HMA Overlays on Rubblized PCC Pavements: State of the Practice
[9]  
Deighton Associates Limited, 2011, PERF CURV REGR UT US
[10]  
Dhakal N., 2016, International Journal of Pavement Research and Technology, V9, P228, DOI DOI 10.1016/J.IJPRT.2016.05.001