Optimizing the number of crews working in parallel and their work sequence to minimize project duration and cost for repetitive construction projects

被引:1
作者
Abdelbasset, Emad [1 ]
Hassan, Abbas [2 ]
Amer, Nabil H. [3 ]
Khalifa, Yasser A. [1 ]
机构
[1] Mil Tech Coll, Dept Civil Engn, Cairo 11865, Egypt
[2] Mil Tech Coll, Dept Prod Management & Qual, Cairo 11865, Egypt
[3] Arab Acad Sci Technol & Marine Transport, Dept Bldg & Construct, Cairo, Egypt
关键词
Project management; Repetitive construction projects; Scheduling; Multi-objective optimization; Time-cost trade-offs; Genetic algorithms; LINE-OF-BALANCE; TRADE-OFF; OPTIMIZATION; TIME; STRATEGY;
D O I
10.1007/s41062-023-01233-3
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Scheduling repetitive construction projects poses a significant challenge in optimally utilizing multiple concurrent crews and sequencing their work to minimize project duration and cost. To address this challenge, this study presents the development of a multi-objective scheduling optimization model for repetitive construction projects consisting of three modules. First, a scheduling module ensures the harmonious coordination of multiple concurrent crews for each activity while considering varying productivity rates, work continuity constraints, and project precedence relationships. Second, a cost module incorporates various contractual cost components to enable a thorough evaluation of project costs and provides flexibility to contractors encountering different contract terms. Third, an optimization module utilizes a genetic algorithm to identify optimal combinations of crews working in parallel and their optimal work sequence, to simultaneously minimize project duration and cost. An application example from the literature was analyzed to validate the model and demonstrate its superiority over previous models. The results showed significant reductions of 8% and 0.78% in project duration and overall costs, respectively, compared to previous models. Furthermore, the capabilities of the model were demonstrated through a real-life case study involving a highway development and renovation project, highlighting its practical benefits and effectiveness in a real-world construction scenario.
引用
收藏
页数:16
相关论文
共 39 条
[1]   Optimization of time and cost through learning curve analysis [J].
Abdelkhalek, Hesham A. ;
Refaie, Hesham S. ;
Aziz, Remon F. .
AIN SHAMS ENGINEERING JOURNAL, 2020, 11 (04) :1069-1082
[2]   Multiobjective Optimization Model for Planning Repetitive Construction Projects [J].
Altuwaim, Ayman ;
El-Rayes, Khaled .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2021, 147 (07)
[3]   Optimizing the Scheduling of Repetitive Construction to Minimize Interruption Cost [J].
Altuwaim, Ayman ;
El-Rayes, Khaled .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2018, 144 (07)
[4]   Minimizing duration and crew work interruptions of repetitive construction projects [J].
Altuwaim, Ayman ;
El-Rayes, Khaled .
AUTOMATION IN CONSTRUCTION, 2018, 88 :59-72
[5]   Optimization of line of balance scheduling considering work interruption [J].
Ammar, Mohammad A. .
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2019, :305-316
[6]   Challenges in line-of-balance scheduling [J].
Arditi, D ;
Tokdemir, OB ;
Suh, K .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2002, 128 (06) :545-556
[7]   LINE-OF-BALANCE SCHEDULING IN PAVEMENT CONSTRUCTION [J].
ARDITI, D ;
ALBULAK, MZ .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1986, 112 (03) :411-424
[8]   Optimizing strategy software for repetitive construction projects within multi-mode resources [J].
Aziz, Remon Fayek .
ALEXANDRIA ENGINEERING JOURNAL, 2013, 52 (03) :373-385
[9]   Optimizing strategy for repetitive construction projects within multi-mode resources [J].
Aziz, Remon Fayek .
ALEXANDRIA ENGINEERING JOURNAL, 2013, 52 (01) :67-81
[10]   Revisiting the concept of natural rhythm of production in line of balance scheduling [J].
Damci, Atilla .
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2022, 22 (12) :2335-2344