Development of delay mitigation measures in construction projects: a combined interpretative structural modeling and MICMAC analysis approach

被引:13
作者
Arantes, Amilcar [1 ]
Ferreira, Luis Miguel D. F. [2 ]
机构
[1] Univ Lisbon, Civil Engn Architecture & Georesources Dept, CERIS, Inst Super Tecn, Lisbon, Portugal
[2] Univ Coimbra, Dept Mech Engn, CEMMPRE, Coimbra, Portugal
关键词
Construction industry; delay causes; interpretive structural modelling; MICMAC analysis; mitigation measures; project management; SUPPLY-CHAIN COMPETITIVENESS; MANAGEMENT-PRACTICES; INFORMATION-SYSTEMS; LITERATURE-REVIEWS; PERFORMANCE; INNOVATION; AGILITY; IMPACT; INTEGRATION; COMPETENCE;
D O I
10.1080/09537287.2022.2163934
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Construction delays are recurrent worldwide, regardless of the type of work, and can result in severe impacts, such as time and cost overruns and conflicts. This work aims to present a methodology to develop mitigation measures for the causes of Delays in Construction Projects (DCPs). Prior works have explored strategies to develop these measures but systematically failed to consider that the interrelationships among causes affect the significance of the impact of each cause. The methodology proposed combines the Interpretative Structural Modelling (ISM) and Matrix Cross Impact Matrix Multiplication (MICMAC) analyses approaches and is grounded on the opinions of construction experts collected during Focus Group Interviews (FGI). First, the critical causes of DCPs are identified. Second, the ISM model is built, representing the interrelationships between the causes and their hierarchy. Third, the MICMAC analysis is performed, revealing the strengths of the relationships among the influencing causes. Fourth, mitigation measures are developed to address the root causes identified in the previous steps, but they are designed to target and mitigate other causes, given their hierarchical relationships, driving power, and levels of dependence. Applying this methodology to the Portuguese context revealed 16 critical causes, which were then hierarchized into six levels of influence. Inadequate bidding and contract award processes and deficient communication between parties were deemed root causes, and 23 measures were put forward to mitigate DCPs. Therefore, this study contributes to the body of knowledge by designing an innovative and practitioner-wise methodology to develop mitigation measures in relation to DCPs and revealing some measures for the Portuguese context.
引用
收藏
页码:1164 / 1179
页数:16
相关论文
共 67 条
[21]   Analysing factors affecting delays in Indian construction projects [J].
Doloi, Hemanta ;
Sawhney, Anil ;
Iyer, K. C. ;
Rentala, Sameer .
INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2012, 30 (04) :479-489
[22]  
Duperrin J.C., 1973, Methode de hierarchisation des elements d'un systeme Essai de prospective du systeme de l'energie nucleaire dans son contexte societal
[23]   Construction Disputes in the UAE: Causes and Resolution Methods [J].
El-Sayegh, Sameh ;
Ahmad, Irtishad ;
Aljanabi, Malak ;
Herzallah, Rawan ;
Metry, Samuel ;
El-Ashwal, Omar .
BUILDINGS, 2020, 10 (10)
[24]   Purchasing and supply management in the construction industry [J].
Ellegaard, Chris ;
Bygballe, Lena E. ;
Dubois, Anna ;
Bankvall, Lars .
JOURNAL OF PURCHASING AND SUPPLY MANAGEMENT, 2010, 16 (04) :219-220
[25]   Delays and cost overruns in the construction projects in the Gaza Strip [J].
Enshassi, Adnan ;
Al-Najjar, Jomah ;
Kumaraswamy, Mohan .
JOURNAL OF FINANCIAL MANAGEMENT OF PROPERTY AND CONSTRUCTION, 2009, 14 (02) :126-+
[26]   Significant factors causing delay in the UAE construction industry [J].
Faridi, Arshi Shakeel ;
El-Sayegh, Sameh Monir .
CONSTRUCTION MANAGEMENT AND ECONOMICS, 2006, 24 (11) :1167-1176
[27]  
Frimpong Y., 2003, International Journal of Project Management, V21, P321, DOI 10.1016/S0263-7863(02)00055-8
[28]   Barriers to the transition towards off-site construction in China: An Interpretive structural modeling approach [J].
Gan, Xiaolong ;
Chang, Ruidong ;
Zuo, Jian ;
Wen, Tao ;
Zillante, George .
JOURNAL OF CLEANER PRODUCTION, 2018, 197 :8-18
[29]   Quantification of Delay Factors Using the Relative Importance Index Method for Construction Projects in Turkey [J].
Gunduz, Murat ;
Nielsen, Yasemin ;
Ozdemir, Mustafa .
JOURNAL OF MANAGEMENT IN ENGINEERING, 2013, 29 (02) :133-139
[30]   Acceptance of the Incentive/Disincentive Contracting Strategy in Developing Construction Markets: Empirical Study from India [J].
Hasan, Abid ;
Jha, Kumar Neeraj .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2016, 142 (02)