Spatio-temporal optimization of construction elevator planning in high-rise building projects

被引:2
作者
Wu, Keyi [1 ]
de Soto, Borja Garcia [1 ]
机构
[1] New York Univ Abu Dhabi, Div Engn, SMART Construct Res Grp, Abu Dhabi, U Arab Emirates
关键词
Construction hoist; Temporary elevator; Vertical transportation; Mixed-integer programming; TRANSPORTATION; SIMULATION; HOIST; TIME;
D O I
10.1016/j.dibe.2024.100328
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Appropriate construction elevator planning is beneficial for successfully completing high-rise building projects. Construction elevator planning typically remains unchanged throughout a high-rise building project or seldom involves the designation of service days, which causes such planning not to respond effectively to variable transportation demands and adversely affects the possibility of further optimization. Another limitation is that the installation and dismantlement dates of construction elevators, which are highly important when multiple construction elevators are used, cannot be explicitly determined in construction elevator planning. To solve these weaknesses, this paper proposes an approach to assign construction elevator cabs to serve designated days and floors based on actual transportation demands from the perspective of spatio-temporal optimization with mixedinteger programming. The experimental case study results show that the presented planning can significantly reduce the total cost when compared to other planning and can provide evidence and explanation for determining the installation and dismantlement dates of construction elevators.
引用
收藏
页数:25
相关论文
共 18 条
[11]   Mixed integer programming [J].
Lee, Jon ;
Letchford, Adam N. .
DISCRETE OPTIMIZATION, 2007, 4 (01) :1-2
[12]   Lifting demand-based zoning for minimizing worker vertical transportation time in high-rise building construction [J].
Park, Moonseo ;
Ha, Sungbong ;
Lee, Hyun-Soo ;
Choi, Yoon-Ki ;
Kim, Hyunsoo ;
Han, Sangwon .
AUTOMATION IN CONSTRUCTION, 2013, 32 :88-95
[13]   Simulation model incorporating genetic algorithms for optimal temporary hoist planning in high-rise building construction [J].
Shin, Yoonseok ;
Cho, Hunhee ;
Kang, Kyung-In .
AUTOMATION IN CONSTRUCTION, 2011, 20 (05) :550-558
[14]  
Wu K., 2019, 36 INT S AUT ROB CON, P99, DOI [10.22260/ISARC2019/0014, DOI 10.22260/ISARC2019/0014]
[15]   Spatio-temporal planning for tower cranes in construction projects with simulated annealing [J].
Wu, Keyi ;
de Soto, Borja Garcia ;
Zhang, Feilian .
AUTOMATION IN CONSTRUCTION, 2020, 111
[16]   BIM-based estimation of vertical transportation demands during the construction of high-rise buildings [J].
Wu, Keyi ;
de Soto, Borja Garcia ;
Adey, Bryan T. ;
Zhang, Feilian .
AUTOMATION IN CONSTRUCTION, 2020, 110
[17]   Optimization of flexible lift processes on high-rise building construction sites [J].
Yazdi, Alireza Jalali ;
Forsythe, Perry ;
Fini, Alireza Ahmadian Fard ;
Maghrebi, Mojtaba .
AUTOMATION IN CONSTRUCTION, 2019, 107
[18]   Mathematical model to optimally solve the lift planning problem in high-rise construction projects [J].
Yazdi, Alireza Jalali ;
Maghrebi, Mojtaba ;
Bazaz, Jafar Bolouri .
AUTOMATION IN CONSTRUCTION, 2018, 92 :120-132