Influence of Track Typology on the Dynamic Response of Short-Span High-Speed Railway Bridges

被引:1
作者
Martinez, Elena Pilar [1 ,2 ]
Ulzurrun, Gonzalo S. D. [2 ]
Zanuy, Carlos [2 ]
机构
[1] MC2 Estudio Ingn, Madrid, Spain
[2] Univ Politecn Madrid, Dept Continuum Mech & Struct, ETS Ingn Caminos Canales & Puertos, Madrid, Spain
来源
HORMIGON Y ACERO | 2023年 / 74卷 / 301期
关键词
Dynamics; high-speed railway bridges; train loads; ballasted track; ballastless track;
D O I
10.33586/hya.2023.3120
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
It is known that short-span high-speed railway viaducts are prone to suffer significant dynamic effects due to the passage of moving train loads. Recent technological advances in railway engineering have resulted in track typologies different from the conventional ballasted track consisting of discrete sleepers fastened to the rails and resting on a ballast bed. In particular, ballastless track has been identified as an effective solution due to reduced maintenance costs, high track stability and excellent geometric quality. Though different track typologies are available in the market, they can be classified as monolithic or independent according to the interaction degree with the bridge girder. In the present paper, the dynamic behaviour of short-span bridges is numerically studied by taking into account the track -bridge interaction by modelling explicitly the components of the track. Two types of ballastless track (monolithic continuous slab and independent short slabs) and conventional ballasted track are considered on simply supported bridges with span length in the range of 15-25 m subjected to envelope and commercial train loads at speeds between 200 and 360 km/h. In total, 2448 numerical cases have been analyzed. The study shows that dynamic deflections and accelerations produced at the bridge girder by moving train loads can be reduced when the ballasted track is replaced to ballastless track systems, especially for the critical speeds higher than 300 km/h. Moreover, it is shown that the two ballastless track systems lead to very similar results, with the monolithic system resulting in slightly smaller bridge deflections and also moderately larger accelerations.
引用
收藏
页码:7 / 20
页数:14
相关论文
共 29 条
[1]  
Acuna J., 1928, Puentes sobre el rio Guadalquivir y sobre el arroyo de los Santos, carretera de 3er orden de la Venta de Santa Amalia a la del Sereno. Tercer presupuesto adicional al de agotamientos, aprobado para realizar las fundaciones y recalces de las pilas del puente, P2
[2]  
Aedo F., 1909, Proyecto de puente metalico sobre el rio Guadalquivir, carretera de 3er orden de la Venta de Santa Amalia en la de Madrid a Cadiz a la del Sereno en la de Bailen a Malaga, P3
[3]  
Aedo F., 1909, Proyecto de puente metalico sobre el rio Guadalquivir, carretera de 3er orden de la Venta de Santa Amalia en la de Madrid a Cadiz a la del Sereno en la de Bailen a Malaga, P20
[4]  
Aedo F, 1907, Proyecto de carretera de 3er orden de la Venta de Santa Amalia en la de Madrid a Cadiz a la del Sereno en la de Bailen a Malaga. Seccion primera, entre Espeluy y la Venta de Santa Amalia, P2
[5]  
Aedo F., 1909, Proyecto de puente metalico sobre el rio Guadalquivir, carretera de 3er orden de la Venta de Santa Amalia en la de Madrid a Cadiz a la del Sereno en la de Bailen a Malaga, P6
[6]  
[Anonymous], Expediente personal del ingeniero de Caminos Francisco Navarro y Navarro
[7]  
Cobos F., 1917, La Ilustracion Espanola y Americana, V30, P478
[8]  
de Zafra J.M., 1911, Construcciones de hormigon armado, P533
[9]  
de Zafra J.M., 1907, Compania de los Ferrocarriles Suburbanos de Malaga. Proyecto de puente de hormigon armado sobre el rio Velez, P2
[10]  
de Zafra J.M, 1910, Revista de Obras Publicas, V1833, P533