A new interval-valued fuzzy multi-objective approach for project time-cost-quality trade-off problem with activity crashing and overlapping under uncertainty

被引:5
作者
Mahdavi-Roshan, Pouyan [1 ]
Mousavi, Seyed Meysam [1 ]
机构
[1] Shahed Univ, Dept Ind Engn, Tehran, Iran
关键词
Project scheduling; Time-cost-; quality trade-off; Crashing; Overlapping; Interval-valued fuzzy sets; DISCRETE-TIME; PORTFOLIO SELECTION; SCHEDULING PROBLEM; MODEL; MANAGEMENT; RISK; OPTIMIZATION; ALGORITHMS; RESOURCES; PRODUCT;
D O I
10.1108/K-11-2021-1217
中图分类号
TP3 [计算技术、计算机技术];
学科分类号
0812 ;
摘要
Purpose Most projects are facing delays, and accelerating the pace of project progress is a necessity. Project managers are responsible for completing the project on time with minimum cost and with maximum quality. This study provides a trade-off between time, cost, and quality objectives to optimize project scheduling. Design/methodology/approach The current paper presents a new resource-constrained multi-mode time-cost-quality trade-off project scheduling model with lags under finish-to-start relations. To be more realistic, crashing and overlapping techniques are utilized. To handle uncertainty, which is a source of project complexity, interval-valued fuzzy sets are adopted on several parameters. In addition, a new hybrid solution approach is developed to cope with interval-valued fuzzy mathematical model that is based on different alpha-levels and compensatory methods. To find the compatible solution among conflicting objectives, an arithmetical average method is provided as a compensatory approach. Findings The interval-valued fuzzy sets approach proposed in this paper is denoted to be scalable, efficient, generalizable and practical in project environments. The results demonstrated that the crashing and overlapping techniques improve time-cost-quality trade-off project scheduling model. Also, interval-valued fuzzy sets can properly manage expressions of the uncertainty of projects which are realistic and practical. The proposed mathematical model is validated by solving a medium-sized dataset an adopted case study. In addition, with a sensitivity analysis approach, the solutions are compared and the model performance is confirmed. Originality/value This paper introduces a new continuous-based, resource-constrained, and multi-mode model with crashing and overlapping techniques simultaneously. In addition, a new hybrid compensatory solution approach is extended based on different alpha-levels to handle interval-valued fuzzy multi-objective mathematical model of project scheduling with influential uncertain parameters.
引用
收藏
页码:4731 / 4759
页数:29
相关论文
共 65 条
[1]   A Multi-Objective Imperialist Competitive Algorithm for solving discrete time, cost and quality trade-off problems with mode-identity and resource-constrained situations [J].
Afruzi, Elham Nabipoor ;
Najafi, Amir Abbas ;
Roghanian, Emad ;
Mazinani, Mostafa .
COMPUTERS & OPERATIONS RESEARCH, 2014, 50 :80-96
[2]   Network decomposition-based benchmark results for the discrete time-cost tradeoff problem [J].
Akkan, C ;
Drexl, A ;
Kimms, A .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2005, 165 (02) :339-358
[3]   The contractor time-cost-credit trade-off problem: integer programming model, heuristic solution, and business insights [J].
Al-Shihabi, Sameh ;
AlDurgam, Mohammad M. .
INTERNATIONAL TRANSACTIONS IN OPERATIONAL RESEARCH, 2020, 27 (06) :2841-2877
[4]  
[Anonymous], 2013, P NEW DEV STRUCTURAL
[5]   INTUITIONISTIC FUZZY-SETS [J].
ATANASSOV, KT .
FUZZY SETS AND SYSTEMS, 1986, 20 (01) :87-96
[6]  
Atkinson R., 1999, International Journal of Project Management, V17, P337, DOI [DOI 10.1016/S0263-7863(98)00069-6, https://doi.org/10.1016/S0263-7863(98)00069-6]
[7]   Project management with time, cost, and quality considerations [J].
Babu, AJG ;
Suresh, N .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1996, 88 (02) :320-327
[8]   Non-linear time-cost trade-off models of activity crashing: Application to construction scheduling and project compression with fast-tracking [J].
Ballesteros-Perez, Pablo ;
Elamrousy, Kamel Mohamed ;
Carmen Gonzalez-Cruz, Ma .
AUTOMATION IN CONSTRUCTION, 2019, 97 :229-240
[9]  
Castillo O., 2019, TYPE 2 FUZZY LOGIC C, P173
[10]   Multi-criteria analysis of supply chain risk management using interval valued fuzzy TOPSIS [J].
Chatterjee K. ;
Kar S. .
OPSEARCH, 2016, 53 (3) :474-499