Long-Term Performance Assessment of a Geosynthetic-Reinforced Railway Substructure

被引:4
作者
Esen, Ahmet F. [1 ,2 ]
Woodward, Peter K. [2 ]
Laghrouche, Omar [1 ]
Connolly, David P. [2 ]
机构
[1] Heriot Watt Univ, Inst Infrastruct & Environm, Edinburgh EH14 4AS, Scotland
[2] Univ Leeds, Inst High Speed Rail & Syst Integrat, Leeds LS2 9JT, England
基金
英国工程与自然科学研究理事会;
关键词
full-scale testing; railway track settlement; geosynthetic-reinforced soil; ballasted track; slab track; SETTLEMENT MODELS; SOIL STRUCTURES; BRIDGE; DESIGN; CONSTRUCTION; SIMULATION; FACILITY;
D O I
10.3390/su15129364
中图分类号
X [环境科学、安全科学];
学科分类号
08 ; 0830 ;
摘要
Significant savings in carbon emissions, cost, and time could be achieved via the reduction in maintenance frequency, capital costs of track construction, and land used. Geosynthetic-reinforced soils offer such sustainable solutions. The experimental work presented in this paper investigates the long-term performance of a Geosynthetic-Reinforced Soil Retaining Wall (GRS-RW) system as an alternative to the conventional railway embankment. Full-scale testing was carried out on three sleeper sections of ballasted and slab tracks by simulating train loads cyclically, phased to 360 km/h. The tracks were supported by either a low-level fully confined conventional embankment or a GRS-RW substructure. The substructures were formed of a 1.2 m deep subgrade and frost protection layer, in accordance with high-speed railway design standards. The overall aim was to assess the performance of the tracks, in terms of transient displacements and total settlements. It was observed that once the GRS-RW system reached its active state, it deformed in a very similar way to a conventional embankment despite the fact that the GRS-RW system is less confined than the conventional embankment. The results indicate that the cumulative settlement of the slab track, which is due to the plastic deformation of the soil, is significantly less than that of the ballasted track, which is primarily caused by the movement of the ballast particles.
引用
收藏
页数:24
相关论文
共 49 条
[1]   Effect of Sleeper Interventions on Railway Track Performance [J].
Abadi, Taufan ;
Le Pen, Louis ;
Zervos, Antonis ;
Powrie, William .
JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINEERING, 2019, 145 (04)
[2]   A Review and Evaluation of Ballast Settlement Models using Results from the Southampton Railway Testing Facility (SRTF) [J].
Abadi, Taufan ;
Le Pen, Louis ;
Zervos, Antonis ;
Powrie, William .
ADVANCES IN TRANSPORTATION GEOTECHNICS III, 2016, 143 :999-1006
[3]  
[Anonymous], 1990, TRRL ROAD NOTE 8 USE
[4]  
ASTM Committee D-18 on Soil and Rock, 2017, STANDARD TEST METHOD
[5]  
Berg R., 2009, FHWANHI10025 NAT HIG
[6]   The Nottingham railway test facility, UK [J].
Brown, S. F. ;
Brodrick, B. V. ;
Thom, N. H. ;
McDowell, G. R. .
PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-TRANSPORT, 2007, 160 (02) :59-65
[7]  
BS 1377-4-1990, 1990, METHODS TEST SOILS C
[8]   Full scale laboratory testing of ballast and concrete slab tracks under phased cyclic loading [J].
Cebasek, T. Marolt ;
Esen, A. F. ;
Woodward, P. K. ;
Laghrouche, O. ;
Connolly, D. P. .
TRANSPORTATION GEOTECHNICS, 2018, 17 :33-40
[9]   Numerical modelling of ground borne vibrations from high speed rail lines on embankments [J].
Connolly, D. ;
Giannopoulos, A. ;
Forde, M. C. .
SOIL DYNAMICS AND EARTHQUAKE ENGINEERING, 2013, 46 :13-19
[10]   Field testing and analysis of high speed rail vibrations [J].
Connolly, D. P. ;
Kouroussis, G. ;
Woodward, P. K. ;
Costa, P. Alves ;
Verlinden, O. ;
Forde, M. C. .
SOIL DYNAMICS AND EARTHQUAKE ENGINEERING, 2014, 67 :102-118