Optimization of Stochastic Repetitive Construction Projects: Minimizing Duration Uncertainties

被引:0
作者
Abosamra, Hussein [1 ]
ElSayad, Mohamed A. [1 ]
Eid, Mohamed S. [1 ]
Elhakeem, Ahmed [1 ]
机构
[1] Arab Acad Sci Technol & Maritime Transport, Dept Construct & Bldg Engn, Cairo, Egypt
来源
COMPUTING IN CIVIL ENGINEERING 2023-VISUALIZATION, INFORMATION MODELING, AND SIMULATION | 2024年
关键词
MODEL; LOB;
D O I
暂无
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
Various studies aimed to optimize the schedules of repetitive projects using line of balance (LOB) via different meta-heuristic optimization techniques. However, most studies considered constant productivity rates to complete activities' units, disregarding the stochastic nature of the construction methods. This paper aims to minimize the uncertainties of the total project duration in non-serial repetitive projects using non-dominated sorting genetic algorithm II optimization (NSGA II). This is achieved through (1) developing a generic scheduling module for repetitive projects using best practices for LOB, (2) utilizing Monte Carlo simulation to assess the effect of uncertainties of crews' productivity rates on the total project duration, and (3) implementing NSGA II to optimize the total project duration and minimize the overall standard deviation of the stochastic project schedule. The presented model would thus help planners and decision-makers to define the optimal schedules that decrease the uncertainties in meeting the scheduled project due date, thus decreasing the overall project risk.
引用
收藏
页码:180 / 188
页数:9
相关论文
共 50 条
[31]   Stochastic logistic fuzzy maps for the construction of integrated multirates scenarios in the financing of infrastructure projects [J].
David Gonzalez-Ruiz, Juan ;
Pena, Alejandro ;
Alexander Duque, Eduardo ;
Patino, Alejandro ;
Chiclana, Francisco ;
Gongora, Mario .
APPLIED SOFT COMPUTING, 2019, 85
[32]   Comparison of SOM-based optimization and particle swarm optimization for minimizing the construction time of a secant pile wall [J].
Chen, Jieh-Haur ;
Yang, Li-Ren ;
Su, Mu-Chun .
AUTOMATION IN CONSTRUCTION, 2009, 18 (06) :844-848
[33]   Stochastic optimization for minimizing operational costs in smart hybrid energy networks considering electric vehicle [J].
Qamar, Nouman ;
Alqahtani, Mohammed ;
Rehan, Muhammad ;
Ahmed, Ijaz ;
Khalid, Muhammad .
PLOS ONE, 2025, 20 (06)
[34]   Customized particle swarm optimization for harmonizing multi-section construction projects [J].
Tomczak, Michal ;
Jaskowski, Piotr .
AUTOMATION IN CONSTRUCTION, 2024, 162
[35]   Achieving improved performance in construction projects: advanced time and cost optimization framework [J].
Pham, Vu Hong Son ;
Dang, Nghiep Trinh Nguyen ;
Nguyen, Van Nam .
EVOLUTIONARY INTELLIGENCE, 2024, 17 (04) :2885-2897
[36]   Scheduling of repetitive construction projects using geographic information systems: an integration of critical path method and line of balance [J].
Tomar A. ;
Bansal V.K. .
Asian Journal of Civil Engineering, 2019, 20 (4) :549-562
[37]   Cost Optimization of Repetitive Projects with Varying Production Rates Using a Max-Min Ant System [J].
Dolabi, Hamid Reza Zolfaghar ;
Afshar, Abbas .
CONSTRUCTION RESEARCH CONGRESS 2016: OLD AND NEW CONSTRUCTION TECHNOLOGIES CONVERGE IN HISTORIC SAN JUAN, 2016, :636-646
[38]   Robustness-based multi-objective optimization for repetitive projects under work continuity uncertainty [J].
Zhang, Lihui ;
Dai, Guyu ;
Zou, Xin ;
Qi, Jianxun .
ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2020, 27 (10) :3095-3113
[39]   Optimization of Renewable Energy Businesses under Operational Level Uncertainties through Extensive Sensitivity Analysis and Stochastic Global Optimization [J].
Salas, S. D. ;
Geraili, A. ;
Romagnoli, J. A. .
INDUSTRIAL & ENGINEERING CHEMISTRY RESEARCH, 2017, 56 (12) :3360-3372
[40]   Sustainable retrofit of petrochemical energy systems under multiple uncertainties using the stochastic optimization method [J].
Qian, Qiming ;
Liu, Hua ;
He, Chang ;
Shu, Yidan ;
Chen, Qing L. ;
Zhang, Bing J. .
COMPUTERS & CHEMICAL ENGINEERING, 2021, 151