Optimization of Stochastic Repetitive Construction Projects: Minimizing Duration Uncertainties

被引:0
作者
Abosamra, Hussein [1 ]
ElSayad, Mohamed A. [1 ]
Eid, Mohamed S. [1 ]
Elhakeem, Ahmed [1 ]
机构
[1] Arab Acad Sci Technol & Maritime Transport, Dept Construct & Bldg Engn, Cairo, Egypt
来源
COMPUTING IN CIVIL ENGINEERING 2023-VISUALIZATION, INFORMATION MODELING, AND SIMULATION | 2024年
关键词
MODEL; LOB;
D O I
暂无
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
Various studies aimed to optimize the schedules of repetitive projects using line of balance (LOB) via different meta-heuristic optimization techniques. However, most studies considered constant productivity rates to complete activities' units, disregarding the stochastic nature of the construction methods. This paper aims to minimize the uncertainties of the total project duration in non-serial repetitive projects using non-dominated sorting genetic algorithm II optimization (NSGA II). This is achieved through (1) developing a generic scheduling module for repetitive projects using best practices for LOB, (2) utilizing Monte Carlo simulation to assess the effect of uncertainties of crews' productivity rates on the total project duration, and (3) implementing NSGA II to optimize the total project duration and minimize the overall standard deviation of the stochastic project schedule. The presented model would thus help planners and decision-makers to define the optimal schedules that decrease the uncertainties in meeting the scheduled project due date, thus decreasing the overall project risk.
引用
收藏
页码:180 / 188
页数:9
相关论文
共 50 条
[21]   Stochastic Project Network Scheduling Technique for Construction Projects Using GERT [J].
Pregina, K. ;
Kannan, M. Ramesh .
ADVANCES IN CONSTRUCTION MANAGEMENT, ACMM 2021, 2022, 191 :381-392
[22]   THE EFFECT OF CURRENT PUBLIC PROCUREMENT LAW ON DURATION AND COST OF CONSTRUCTION PROJECTS IN TURKEY [J].
Erdis, Ercan .
JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2013, 19 (01) :121-135
[23]   A Comparison of the Project Management Methodologies PRINCE2 and PMBOK in Managing Repetitive Construction Projects [J].
Simonaitis, Aivaras ;
Dauksys, Mindaugas ;
Mockiene, Jurate .
BUILDINGS, 2023, 13 (07)
[24]   New Approach to Improve General Contractor Crew's Work Continuity in Repetitive Construction Projects [J].
Tomczak, Michal ;
Jaskowski, Piotr .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2020, 146 (05)
[25]   Stochastic Optimization of Onboard Photovoltaic Hybrid Power System Considering Environmental Uncertainties [J].
Zhu, Jianyun ;
Chen, Li .
JOURNAL OF MARINE SCIENCE AND ENGINEERING, 2024, 12 (08)
[26]   Stochastic Earthmoving Fleet Arrangement Optimization Considering Project Duration and Cost [J].
Mohsenijam, Arash ;
Mahdavian, Amirsaman ;
Shojaei, Alireza .
MODELLING, 2020, 1 (02) :156-174
[27]   Framework for Smart Cost Optimization of Material Logistics in Construction Road Projects [J].
Alanazi, Abdulkareem ;
Al-Gahtani, Khalid ;
Alsugair, Abdullah .
INFRASTRUCTURES, 2022, 7 (05)
[28]   Negotiation for Time Optimization in Construction Projects with Competitive and Social Welfare Preferences [J].
Meng, Qingfeng ;
Li, Zhen ;
Du, Jianguo ;
Liu, Huimin ;
Ding, Xiang .
COMPLEXITY, 2019, 2019
[29]   CVaR-based factorial stochastic optimization of water resources systems with correlated uncertainties [J].
Wang, Y. Y. ;
Huang, G. H. ;
Wang, S. .
STOCHASTIC ENVIRONMENTAL RESEARCH AND RISK ASSESSMENT, 2017, 31 (06) :1543-1553
[30]   A Novel Stochastic Approach for Optimization of Diversion System Dimension by Considering Hydrological and Hydraulic Uncertainties [J].
Sharafati, Ahmad ;
Doroudi, Siyamak ;
Shahid, Shamsuddin ;
Moridi, Ali .
WATER RESOURCES MANAGEMENT, 2021, 35 (11) :3649-3677