Optimization of Stochastic Repetitive Construction Projects: Minimizing Duration Uncertainties

被引:0
|
作者
Abosamra, Hussein [1 ]
ElSayad, Mohamed A. [1 ]
Eid, Mohamed S. [1 ]
Elhakeem, Ahmed [1 ]
机构
[1] Arab Acad Sci Technol & Maritime Transport, Dept Construct & Bldg Engn, Cairo, Egypt
来源
COMPUTING IN CIVIL ENGINEERING 2023-VISUALIZATION, INFORMATION MODELING, AND SIMULATION | 2024年
关键词
MODEL; LOB;
D O I
暂无
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
Various studies aimed to optimize the schedules of repetitive projects using line of balance (LOB) via different meta-heuristic optimization techniques. However, most studies considered constant productivity rates to complete activities' units, disregarding the stochastic nature of the construction methods. This paper aims to minimize the uncertainties of the total project duration in non-serial repetitive projects using non-dominated sorting genetic algorithm II optimization (NSGA II). This is achieved through (1) developing a generic scheduling module for repetitive projects using best practices for LOB, (2) utilizing Monte Carlo simulation to assess the effect of uncertainties of crews' productivity rates on the total project duration, and (3) implementing NSGA II to optimize the total project duration and minimize the overall standard deviation of the stochastic project schedule. The presented model would thus help planners and decision-makers to define the optimal schedules that decrease the uncertainties in meeting the scheduled project due date, thus decreasing the overall project risk.
引用
收藏
页码:180 / 188
页数:9
相关论文
共 50 条
  • [1] Stochastic scheduling optimization of repetitive construction projects to minimize project duration and cost
    Hassan, Abbas
    El-Rayes, Khaled
    Attalla, Mohamed
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2023, 23 (09) : 1447 - 1456
  • [2] Minimizing duration and crew work interruptions of repetitive construction projects
    Altuwaim, Ayman
    El-Rayes, Khaled
    AUTOMATION IN CONSTRUCTION, 2018, 88 : 59 - 72
  • [3] Minimizing the Duration of Repetitive Construction Processes with Work Continuity Constraints
    Jaskowski, Piotr
    Biruk, Slawomir
    COMPUTATION, 2019, 7 (01):
  • [4] Multiobjective Optimization Model for Planning Repetitive Construction Projects
    Altuwaim, Ayman
    El-Rayes, Khaled
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2021, 147 (07)
  • [5] SIMULATION AND OPTIMIZATION FOR CONSTRUCTION REPETITIVE PROJECTS USING PROMODEL AND SIMRUNNER
    Srisuwanrat, Chachrist
    Ioannou, Photios G.
    Tsimhoni, Omer
    2008 WINTER SIMULATION CONFERENCE, VOLS 1-5, 2008, : 2402 - +
  • [6] Linear Scheduling Optimization Model for Planning Repetitive Construction Projects
    Monghasemi, Shahryar
    Abdallah, Moatassem
    Clevenger, Caroline
    CONSTRUCTION RESEARCH CONGRESS 2020: PROJECT MANAGEMENT AND CONTROLS, MATERIALS, AND CONTRACTS, 2020, : 1129 - 1138
  • [7] Linear Optimization Model for Scheduling Repetitive Construction Projects with Multiple Crews
    Monghasemi, Shahryar
    Abdallah, Moatassem
    CONSTRUCTION RESEARCH CONGRESS 2022: PROJECT MANAGEMENT AND DELIVERY, CONTRACTS, AND DESIGN AND MATERIALS, 2022, : 461 - 471
  • [8] Hybrid Time-Cost Optimization of Nonserial Repetitive Construction Projects
    Ezeldin, A. Samer
    Soliman, Ahmed
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2009, 135 (01) : 42 - 55
  • [9] Multipurpose linear programming optimization model for repetitive activities scheduling in construction projects
    Diego Garcia-Nieves, Juan
    Luis Ponz-Tienda, Jose
    Ospina-Alvarado, Angelica
    Bonilla-Palacios, Mateo
    AUTOMATION IN CONSTRUCTION, 2019, 105
  • [10] War uncertainties delay construction projects
    Stell, J
    OIL & GAS JOURNAL, 2003, 101 (15) : 66 - +