Using Machine Learning to Improve Cost and Duration Prediction Accuracy in Green Building Projects

被引:27
作者
Darko, Amos [1 ]
Glushakova, Iuliia [1 ]
Boateng, Emmanuel B. [2 ]
Chan, Albert P. C. [1 ]
机构
[1] Hong Kong Polytech Univ, Dept Bldg & Real Estate, Kowloon, Hong Kong, Peoples R China
[2] Univ Wollongong, Sch Hlth & Soc, Wollongong, NSW 2522, Australia
关键词
Artificial intelligence; Machine learning (ML); Web application; Accurate cost and duration prediction; Green building projects (GBPs); Project management; SUPPORT VECTOR REGRESSION; ARTIFICIAL NEURAL-NETWORK; MODEL; VARIABLES; TIME;
D O I
10.1061/JCEMD4.COENG-13101
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
A major source of risk in green building projects (GBPs) is inaccurate human prediction of the final project cost and duration, which in turn results in cost and schedule overruns (i.e., poor project performance). This paper presents promising new models to mitigate such risk based upon machine learning (ML). Historical data from 198 GBPs in Hong Kong were used to develop and train two fully connected deep neural networks (DNN) models to learn and predict cost and duration, respectively, based on green building rating (GBR) and other project parameters. The models can predict cost and duration with mean absolute percentage error (MAPE) values of 0.07 and 0.09, respectively. They were then integrated with support vector regression (SVR), and results indicated that the integrated DNN-SVR models improve prediction accuracy, decreasing the MAPE from 0.07 to 0.06 (cost) and 0.09 to 0.07 (duration), respectively. The validated models were for the first time deployed as a ML-based web application for automated, fast, and accurate GBP cost and duration prediction. The feature importance analysis results revealed that the most influential parameters on the GBP cost and duration are project area and weather, respectively, not the GBR. Theoretically, the outcomes of this study provide new insights into the impact of GBR on project cost and duration, which are useful for the promotion of GBPs to improve sustainability. Practically, the study provides policymakers and practitioners with novel ML-based models and a web application to improve GBP delivery performance.
引用
收藏
页数:21
相关论文
共 106 条
[1]  
Abergel T., 2019, GLOBAL STATUS REPORT
[2]   Statistical Analysis on the Cost and Duration of Public Building Projects [J].
Abu Hammad, Ayman A. ;
Ali, Souma M. Alhaj ;
Sweis, Ghaleb J. ;
Sweis, Rateb J. .
JOURNAL OF MANAGEMENT IN ENGINEERING, 2010, 26 (02) :105-112
[3]  
Agarap AF, 2018, arXiv
[4]   Construction cost prediction model for conventional and sustainable college buildings in North America [J].
Alshamrani, Othman Subhi .
JOURNAL OF TAIBAH UNIVERSITY FOR SCIENCE, 2017, 11 (02) :315-323
[5]   Extreme Gradient Boosting-Based Machine Learning Approach for Green Building Cost Prediction [J].
Alshboul, Odey ;
Shehadeh, Ali ;
Almasabha, Ghassan ;
Almuflih, Ali Saeed .
SUSTAINABILITY, 2022, 14 (11)
[6]   Application of support vector machines in assessing conceptual cost estimates [J].
An, Sung-Hoon ;
Park, U-Yeol ;
Kang, Kyung-In ;
Cho, Moon-Young ;
Cho, Hun-Hee .
JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2007, 21 (04) :259-264
[7]  
APM (Association for Project Management), 2008, INT RISK EARN VAL MA
[8]   A survey of cross-validation procedures for model selection [J].
Arlot, Sylvain ;
Celisse, Alain .
STATISTICS SURVEYS, 2010, 4 :40-79
[9]  
Arun C. S., 2012, P WORLD CONSTR C 201, P62
[10]   Predicting cost deviation in reconstruction projects: Artificial neural network versus regression [J].
Attalla, M ;
Hegazy, T .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2003, 129 (04) :405-411