A DRL-Based Load Shedding Strategy Considering Communication Delay for Mitigating Power Grid Cascading Failure

被引:2
作者
Wei, Yongjing [1 ]
Tian, Anqi [1 ]
Jiang, Yingjie [1 ]
Zhang, Wenjian [2 ]
Ma, Liqiang [2 ]
Ma, Liang [1 ]
Sun, Chao [1 ]
Sun, Jian [2 ]
机构
[1] State Grid Shandong Elect Power Co, Informat & Telecommun Co, Jinan 250013, Peoples R China
[2] Shandong Univ, Sch Informat Sci & Engn, Shandong Prov Key Lab Wireless Commun Technol, Qingdao 266237, Peoples R China
关键词
power grid; power communication network; DC power flow model; cascading failures; DRL; load shedding strategy; SAC;
D O I
10.3390/electronics12143024
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
Successive failures in power transmission lines can cause cascading failures in the power grid, which may eventually affect large parts of the power grid and even cause the power grid system to go down. Collecting and transmitting primary equipment information and issuing load-shedding action commands in the power grid depend on the power communication network. With the help of the power communication network, we can better observe the situation of the power grid in real time and provide a guarantee for the regular working of the power grid. However, the communication network also has the problem of communication delay causing latency in load-shedding action. On the premise of preserving the key physical properties and operational characteristics of the power grid, this paper uses the IEEE 14 and 30 bus systems as examples to establish a direct current (DC) power flow simulation environment. We establish a communication network model based on the power grid topology and the corresponding communication channels. For the problem of cascading failures occurring in the power grid after transmission line failures, a load-shedding strategy using soft actor-critic (SAC) based on deep reinforcement learning (DRL) was developed to effectively mitigate cascading failures in the power grid while considering the impact of communication delay. The corresponding communication delay is obtained by calculating the shortest communication path using the Dijkstra algorithm. The simulation verifies the feasibility and effectiveness of the SAC algorithm to mitigate cascading failures. The trained network can decide on actions and give commands quickly when a specific initial failure is encountered, reducing the scale of cascading failures.
引用
收藏
页数:20
相关论文
共 15 条
[11]   Vulnerable Line Identification of Cascading Failure in Power Grid Based on New Electrical Betweenness [J].
Chen, Chao-Yang ;
Zhou, Yong ;
Wang, Yanwu ;
Ding, Li ;
Huang, Tingwen .
IEEE TRANSACTIONS ON CIRCUITS AND SYSTEMS II-EXPRESS BRIEFS, 2023, 70 (02) :665-669
[12]   New design of intelligent load shedding algorithm based on critical line overloads to reduce network cascading failure riskse [J].
Majidi, Mehrad ;
Aghamohammadi, Mohammad-Reza ;
Manbachi, Moein .
TURKISH JOURNAL OF ELECTRICAL ENGINEERING AND COMPUTER SCIENCES, 2014, 22 (06) :1395-1409
[13]   Frequency Control Strategy After Receiving-End Power Grid Splitting Considering Load Characteristics [J].
Lou Y. ;
Jiang R. ;
Qian F. ;
Duan Q. ;
Luo G. ;
Wu S. ;
Liu J. ;
Zhang Z. ;
Sun Y. .
Dianwang Jishu/Power System Technology, 2019, 43 (01) :213-220
[14]   Risk assessment method for power grid communication link failure based on fuzzy comprehensive assessment [J].
Mo, Lianguang ;
Wei, Liang .
INTERNATIONAL JOURNAL OF INTERNET PROTOCOL TECHNOLOGY, 2022, 15 (02) :69-75
[15]   Screening indices and Search Strategy for AC-DC Hybrid Receiving-end Power Grid Cascading Failures Based on Hybrid Electromechanical-electromagnetic Simulation [J].
Bian X. ;
Yang Y. ;
Huang R. ;
Zhou Q. ;
Wang X. ;
Li D. .
Zhongguo Dianji Gongcheng Xuebao/Proceedings of the Chinese Society of Electrical Engineering, 2023, 43 (17) :6614-6627