Modeling duration of building renovation projects

被引:4
|
作者
Lawal, Haruna Sa'idu [1 ]
Ahmadu, Hassan Adaviriku [1 ]
Abdullahi, Muhammad [1 ]
Yamusa, Muhammad Aliyu [1 ]
Abdulrazaq, Mustapha [1 ]
机构
[1] Ahmadu Bello Univ, Dept Quant Surveying, Kaduna, Nigeria
关键词
Artificial neural network; Construction; Duration; Modeling; Renovation; Prediction; Project; NEURAL-NETWORK; CONSTRUCTION; COST; TIME; DELAY;
D O I
10.1108/JFMPC-06-2022-0030
中图分类号
F8 [财政、金融];
学科分类号
0202 ;
摘要
PurposeThis study aims to develop a building renovation duration prediction model incorporating both scope and non-scope factors. Design/methodology/approachThe study used a questionnaire to obtain basic information relating to identified project scope factors as well as information relating to the impact of the non-scope factors on the duration of building renovation projects. The study retrieved 121 completed questionnaires from construction firms on tertiary education trust fund (TETFund) building renovation projects. Artificial neural network was then used to develop the model using 90% of the data, while mean absolute percentage error was used to validate the model using the remaining 10% of the data. FindingsTwo artificial neural network models were developed - a multilayer perceptron (MLP) and a radial basis function (RBF) model. The accuracy of the models was 86% and 80%, respectively. The developed models' predictions were not statistically different from those of actual duration estimates with less than 20% error margin. Also, the study found that MLP models are more accurate than RBF models. Research limitations/implicationsThe developed models are only applicable to projects that suit the characteristics and nature of the data used to develop the models. Hence, models can only predict the duration of building renovation projects. Practical implicationsThe developed models are expected to serve as a tool for realistic estimation of the duration of building renovation projects and thus, help construction project managers to effectively plan and manage it. Social implicationsThe developed models are expected to serve as a tool for realistic estimation of the duration of building renovation projects and thus, help construction project managers to effectively plan and manage it; it also helps clients to effectively benchmark projects duration and contractors to accurately estimate duration at tendering stage. Originality/valueThe study presents models that combine both scope and non-scope factors in predicting the duration of building renovation projects so as to ensure more realistic predictions.
引用
收藏
页码:423 / 438
页数:16
相关论文
共 50 条
  • [1] ESTIMATING NORMAL DURATION OF RENOVATION FOR MULTISTORY APARTMENT BUILDING CONSIDERING EXTENSION-TYPE RENOVATION PROJECTS
    Yoon, Jongsik
    Yu, Ilhan
    JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2019, 25 (02) : 156 - 167
  • [2] Quantitative evaluation and modelling of uncertainty factors impacting duration of building renovation projects
    Yamusa, Muhammad Aliyu
    Dandago, Abdulmalik Abba
    Lawal, Haruna Sa'idu
    Saka, Abdullahi B.
    Abubakar, Mu'awiya
    Abdullahi, Muhammad
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2025,
  • [3] IN PROGRESS + 5 BUILDING RENOVATION PROJECTS
    不详
    PROGRESSIVE ARCHITECTURE, 1976, 57 (11): : 34 - 34
  • [4] Literature review of Building Information Modeling (BIM) intended for the purpose of renovation projects
    Joblot, L.
    Paviot, T.
    Deneux, D.
    Lamouri, S.
    IFAC PAPERSONLINE, 2017, 50 (01): : 10518 - 10525
  • [5] Takt Planning in Apartment Building Renovation Projects
    Keskiniva, Kimmo
    Saari, Arto
    Junnonen, Juha-Matti
    BUILDINGS, 2020, 10 (12) : 1 - 17
  • [6] A digital construction framework integrating building information modeling and reverse engineering technologies for renovation projects
    Ding, Zhikun
    Liu, Shan
    Liao, Longhui
    Zhang, Liang
    AUTOMATION IN CONSTRUCTION, 2019, 102 : 45 - 58
  • [7] A Final Cost Estimating Model for Building Renovation Projects
    Papadimitriou, Vasso E.
    Aretoulis, Georgios N.
    BUILDINGS, 2024, 14 (04)
  • [8] Impact of uncertainty factors on the performance of building renovation projects
    Dandago, Abdulmalik Abba
    Yamusa, Muhammad Aliyu
    Lawal, Haruna Sa'idu
    Abubakar, Mu'awiya
    Abdullahi, Muhammad
    Zailani, Bello Mahmud
    JOURNAL OF ENGINEERING DESIGN AND TECHNOLOGY, 2025,
  • [9] Optimized scheduling method for office building renovation projects
    Cho, Kyuman
    Kim, Taehoon
    EXPERT SYSTEMS WITH APPLICATIONS, 2021, 168
  • [10] Determinants of construction duration for building projects in Germany
    Dursun, Onur
    Stoy, Christian
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2012, 19 (04) : 444 - +