Comparison of the Stability and Accuracy of Deterministic Project Cost Prediction Methods in Earned Value Management

被引:3
|
作者
Barrientos-Orellana, Alexis [1 ]
Ballesteros-Perez, Pablo [2 ]
Mora-Melia, Daniel [1 ,3 ]
Cerezo-Narvaez, Alberto [4 ]
Gutierrez-Bahamondes, Jimmy H. [5 ]
机构
[1] Univ Talca, Fac Engn, Dept Engn & Construct Management, Camino Niches Km 1, Curico 3340000, Chile
[2] Univ Politecn Valencia, Innovat & Sustainabil Res Ctr PRINS, Project Management, Camino Vera S-N, Valencia 46022, Spain
[3] Univ Politecn Valencia, Dept Hydraul Engn & Environm, Camino Vera S-N, Valencia 46022, Spain
[4] Univ Cadiz, Dept Mech Engn & Ind Design, Avda Univ Cadiz 10, Cadiz 11519, Spain
[5] Univ Talca, Fac Engn, Comp Sci Dept, Camino Niches Km 1, Curico 3340000, Chile
关键词
accuracy; cost prediction methods; earned value analysis; stability; topological structure; DURATION; RISK; PERFORMANCE; COMPLETION; FORECAST; METRICS;
D O I
10.3390/buildings13051206
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Completing a project on time and on budget are essential factors for the success of any project. One technique that allows predicting the final cost of a project is earned value management (EVM). In this technique, different mathematical methods for predicting the final project cost have been proposed over the last 30 years. These formulas make use of activities' actual costs and durations as the project progresses. EVM is a technique widely used by many project management professionals. However, very few studies have compared the stability and accuracy of the multiple existing methods for predicting the final cost of the project (commonly abbreviated as estimated cost at completion, EAC). This study compares the stability and accuracy of 30 deterministic cost prediction methods (EAC) in EVM. For this purpose, a representative database of 4100 simulated projects of various topological structures is used. Our results suggest that the methods with the simplest mathematical configurations achieve better stability and accuracy performance. Knowing which EVM methods are the most stable and accurate for predicting the final cost of the project will help project practitioners choose the most reliable cost prediction techniques when they are managing their own projects in real contexts.
引用
收藏
页数:18
相关论文
共 50 条
  • [1] Stability and accuracy of deterministic project duration forecasting methods in earned value management
    Barrientos-Orellana, Alexis
    Ballesteros-Perez, Pablo
    Mora-Melia, Daniel
    Gonzalez-Cruz, Maria Carmen
    Vanhoucke, Mario
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2022, 29 (03) : 1449 - 1469
  • [2] Prediction of project outcome The application of statistical methods to earned value management and earned schedule performance indexes
    Lipke, Walt
    Zwikael, Ofer
    Henderson, Kym
    Anbari, Frank
    INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2009, 27 (04) : 400 - 407
  • [3] Research on applications of the earned value management in the project cost management
    An, Yuhua
    Liu, Liqun
    Proceedings of 2007 International Conference on Construction & Real Estate Management, Vols 1 and 2, 2007, : 973 - 978
  • [4] Combination of Project Cost Forecasts in Earned Value Management
    Kim, Byung-Cheol
    Reinschmidt, Kenneth F.
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2011, 137 (11): : 958 - 966
  • [5] A comparison of the performance of various project control methods using earned value management systems
    Colin, Jeroen
    Vanhoucke, Mario
    EXPERT SYSTEMS WITH APPLICATIONS, 2015, 42 (06) : 3159 - 3175
  • [6] Earned value project management
    Fleming, Quentin W.
    Koppelman, Joel M.
    Cost Engineering (Morgantown, West Virginia), 1997, 39 (02): : 13 - 15
  • [7] Project management: Earned value management
    Duncan, B
    TECHNOLOGY OF OBJECT-ORIENTED LANGUAGES AND SYSTEMS - TOOLS 34, PROCEEDINGS, 2000, : 513 - 514
  • [8] Probabilistic Evaluation of Cost Performance Stability in Earned Value Management
    Kim, Byung-Cheol
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2016, 32 (01)
  • [9] Empirical Evaluation of Earned Value Management Forecasting Accuracy for Time and Cost
    Batselier, Jordy
    Vanhoucke, Mario
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2015, 141 (11)
  • [10] Project cost forecasting based on earned value management and Markov chain
    Damavandi, Majid
    Tavakoli, Mahdieh
    Jolai, Fariborz
    ANNALS OF OPERATIONS RESEARCH, 2024,