Job shop scheduling problem with alternative machines using genetic algorithms

被引:0
作者
I.A.Chaudhry [1 ]
机构
[1] National University of Sciences and Technology,Islamabad,Pakistan
关键词
alternative machine; genetic algorithm(GA); job shop; scheduling; spreadsheet;
D O I
暂无
中图分类号
TH186 [生产技术管理];
学科分类号
0802 ;
摘要
The classical job shop scheduling problem(JSP) is the most popular machine scheduling model in practice and is known as NP-hard.The formulation of the JSP is based on the assumption that for each part type or job there is only one process plan that prescribes the sequence of operations and the machine on which each operation has to be performed.However,JSP with alternative machines for various operations is an extension of the classical JSP,which allows an operation to be processed by any machine from a given set of machines.Since this problem requires an additional decision of machine allocation during scheduling,it is much more complex than JSP.We present a domain independent genetic algorithm(GA) approach for the job shop scheduling problem with alternative machines.The GA is implemented in a spreadsheet environment.The performance of the proposed GA is analyzed by comparing with various problem instances taken from the literatures.The result shows that the proposed GA is competitive with the existing approaches.A simplified approach that would be beneficial to both practitioners and researchers is presented for solving scheduling problems with alternative machines.
引用
收藏
页码:1322 / 1333
页数:12
相关论文
共 50 条
  • [31] Using two metaheuristic algorithms for scheduling parallel machines with sequence dependent set-up times in job shop industries
    Mohammadi, Ghorbanali
    Moaddabi, Erfan
    INTERNATIONAL JOURNAL OF SYSTEMS SCIENCE, 2021, 52 (14) : 2904 - 2917
  • [32] Tighter Bounds on Preemptive Job Shop Scheduling with Two Machines
    E. J. Anderson
    T. S. Jayram
    T. Kimbrel
    Computing, 2001, 67 : 83 - 90
  • [33] An improved genetic-based particle swarm optimization for job shop scheduling problem
    Niu, Q.
    Gu, X. S.
    DYNAMICS OF CONTINUOUS DISCRETE AND IMPULSIVE SYSTEMS-SERIES B-APPLICATIONS & ALGORITHMS, 2006, 13E : 3312 - 3317
  • [34] On cyclic job shop scheduling problem
    Bozejko, Wojciech
    Wodecki, Mieczyslaw
    2018 IEEE 22ND INTERNATIONAL CONFERENCE ON INTELLIGENT ENGINEERING SYSTEMS (INES 2018), 2018, : 265 - 270
  • [35] Enhanced evolutionary algorithms for single and multiobjective optimization in the job shop scheduling problem
    Esquivel, S
    Ferrero, S
    Gallard, R
    Salto, C
    Alfonso, H
    Schütz, M
    KNOWLEDGE-BASED SYSTEMS, 2002, 15 (1-2) : 13 - 25
  • [36] An optimal method for the preemptive job shop scheduling problem
    Ebadi, Abbas
    Moslehi, Ghasem
    COMPUTERS & OPERATIONS RESEARCH, 2013, 40 (05) : 1314 - 1327
  • [37] Parallel Simulated Annealing for the Job Shop Scheduling Problem
    Bozejko, Wojciech
    Pempera, Jaroslaw
    Smutnicki, Czeslaw
    COMPUTATIONAL SCIENCE - ICCS 2009, PART I, 2009, 5544 : 631 - 640
  • [38] Differential Evolution Algorithm for Job Shop Scheduling Problem
    Wisittipanich, Warisa
    Kachitvichyanukul, Voratas
    INDUSTRIAL ENGINEERING AND MANAGEMENT SYSTEMS, 2011, 10 (03): : 203 - 208
  • [39] Dynamic scheduling of manufacturing job shops using genetic algorithms
    Chryssolouris, G
    Subramaniam, V
    JOURNAL OF INTELLIGENT MANUFACTURING, 2001, 12 (03) : 281 - 293
  • [40] Dynamic scheduling of manufacturing job shops using genetic algorithms
    George Chryssolouris
    Velusamy Subramaniam
    Journal of Intelligent Manufacturing, 2001, 12 : 281 - 293