Optimizing Earth Allocation for Rock-Fill Dam Construction

被引:0
作者
钟登华
胡程顺
张静
机构
[1] School of Civil Engineering
[2] Tianjin University
[3] Tianjin
[4] China
[5] Middle South Hydroelectric Investigation and Design Institute of State Power Company
[6] Changsha
关键词
rock-fill dam construction; earth allocation; dynamic allocation; linear programming;
D O I
暂无
中图分类号
TV641 [土石坝(当地材料坝、填筑坝)];
学科分类号
081504 ;
摘要
An optimal allocation of earth is of great significance to reduce the project cost and duration in the construction of rock-fill dams. The earth allocation is a dynamic system affected by various time-space constraints. Based on previous studies, a new method of optimizing this dynamic system as a static one is presented. In order to build a generalized and flexible model of the problem, some man-made constraints were investigated in building the mathematic model. Linear programming and simplex method are introduced to solve the optimization problem of earth allocation. A case study in a large-scale rock-fill dam construction project is presented to demonstrate the proposed method and its successful application shows the feasibility and effectiveness of the method.
引用
收藏
页码:146 / 151
页数:6