Using Monte Carlo Simulations and Little's Law to Improve Process Planning

被引:0
作者
Grimm, Benjamin [1 ]
Lambert, Michael W. [1 ]
Rakurty, C. S. [1 ]
机构
[1] MK Morse Co, Canton, OH 44707 USA
来源
PROCEEDINGS OF THE CONFERENCE ON PRODUCTION SYSTEMS AND LOGISTICS, CPSL 2024 | 2024年
关键词
Monte Carlo; Little's Law; Process Planning; Scheduling; Queueing Theory;
D O I
10.15488/17767
中图分类号
X [环境科学、安全科学];
学科分类号
08 ; 0830 ;
摘要
Production planning and scheduling are challenging with recent disruptions in the supply chain and increased demand for reduced lead times. With an increased demand for production and ever-changing delivery dates of raw materials, a dynamic production planning model with machine-operator-part-specific historical data is essential for small and medium-scale manufacturers. Based on the sales orders and inventory, machine production rates, and work-in-process information, Little's law estimates the initial lead time. To improve the accuracy of the lead time, a Monte Carlo simulation based on the historical data of the machine-operator-part production rate is used along with the queuing principles and theory of constraints. The theory of constraints is used to facilitate issues such as preventive maintenance, unscheduled machine breakdown, etc. The dynamic nature of the shop floor issues is used to update the Monte Carlo simulations to improve the process flow and the lead time estimation. This model was implemented as a case study at a cutting tool manufacturing plant to reduce lead time and increase customer satisfaction. Finally, the paper reports the case study's findings to estimate the lead time effectively and facilitate the production planning and scheduling process. Overall, the results showed that the model has assisted in reducing the lead times and backorders, proving the present study's hypothesis. Using Little's law and Monte Carlo simulation using realtime data has enabled an accurate estimate of the lead time and improved customer satisfaction.
引用
收藏
页码:799 / 805
页数:7
相关论文
共 15 条
  • [1] AN APPLICATION OF THE MULTISTAGE MONTE-CARLO OPTIMIZATION ALGORITHM TO AGGREGATE PRODUCTION PLANNING
    BAKIR, MA
    BYRNE, MD
    [J]. INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 1994, 35 (1-3) : 207 - 213
  • [2] Operative production planning utilising quantitative forecasting and Monte Carlo simulations
    Fabianova, Jana
    Kacmary, Peter
    Janekova, Jaroslava
    [J]. OPEN ENGINEERING, 2019, 9 (01): : 613 - 622
  • [3] Robustness evaluation of production plans using Monte Carlo simulation
    Franke, Susanne
    Franke, Felix
    Riedel, Ralph
    [J]. 10TH CIRP SPONSORED CONFERENCE ON DIGITAL ENTERPRISE TECHNOLOGIES (DET 2020) - DIGITAL TECHNOLOGIES AS ENABLERS OF INDUSTRIAL COMPETITIVENESS AND SUSTAINABILITY, 2021, 54 : 130 - 135
  • [4] PRODUCT MIX OPTIMIZATION BASED ON MONTE CARLO SIMULATION: A CASE STUDY
    Janekova, J.
    Fabianova, J.
    Izarikova, G.
    Onofrejova, D.
    Kovac, J.
    [J]. INTERNATIONAL JOURNAL OF SIMULATION MODELLING, 2018, 17 (02) : 295 - 307
  • [5] Little's Law in a continuous setting
    Jodlbauer, H
    Stöcher, W
    [J]. INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2006, 103 (01) : 10 - 16
  • [6] Kempf K. G., Planning production and inventories in the extended enterprise: a state of the art handbook
  • [7] Mechanistic cutting force model in band sawing
    Ko, TJ
    Kim, HS
    [J]. INTERNATIONAL JOURNAL OF MACHINE TOOLS & MANUFACTURE, 1999, 39 (08) : 1185 - 1197
  • [8] A metamodel-based Monte Carlo simulation approach for responsive production planning of manufacturing systems
    Li, Minqi
    Yang, Feng
    Uzsoy, Reha
    Xu, Jie
    [J]. JOURNAL OF MANUFACTURING SYSTEMS, 2016, 38 : 114 - 133
  • [9] Rakurty C. S., 2021, P ASME 2021 INT MECH, V2B
  • [10] Rakurty C. S., 2019, Holesaw, Patent No. [10,384,273, 10384273]