Relating measured PUE to the cooling strategy and operating conditions through a review of a number of Maltese data centres

被引:0
作者
Abdilla, Amy [1 ]
Borg, Simon P. [1 ]
Licari, John [2 ]
机构
[1] Univ Malta, Fac Built Environm, Dept Environm Design, Msida Campus, Msida 2080, Malta
[2] Univ Malta, Fac Engn, Dept Elect Engn, Msida Campus, Msida 2080, Malta
关键词
Data Centres; CRAC; Cooling technologies; Cooling strategies; Temperature and humidity; Performance usage effectiveness; Energy-efficiency; THERMAL MANAGEMENT; AIR; CONSUMPTION; EFFICIENCY; LIQUID;
D O I
10.1016/j.egyr.2025.02.013
中图分类号
TE [石油、天然气工业]; TK [能源与动力工程];
学科分类号
0807 ; 0820 ;
摘要
To deal with the heat generated by the information technology equipment hosted in data centres, dedicated cooling systems allowing the information technology systems to operate at their optimum thermal conditions continuously, are typically used. Being constantly in operation these cooling technologies have a large impact on the overall energy performance of these data centres. Based on this premise, the work presented in this research aims at gauging and comparing the real-life performance of three types of data centre cooling strategies found in just as many commercial data centres in Malta. Temperature and humidity logging was carried out to analyse the data centres operating conditions in conjunction with an analysis of the energy performance of the data centres themselves. A well know energy performance metric, the Power Usage Effectiveness, was used to enable the comparison of the energy performance of these data centres with one another. The results obtained revealed that whereas the use of computer room air conditioning is common in modern data centres, significant differences in energy performance can result from the specific application of such cooling systems, mostly related to the use or otherwise of physically segregated cold and hot aisle, the use of direct expansion cooling or air cooled chillers, and the use of direct or variable speed systems. Furthermore, the importance of air flow management in ensuring a uniform temperature throughout was observed through detailed temperature monitoring of one of the aisles in one of the data centres investigated.
引用
收藏
页码:2612 / 2623
页数:12
相关论文
共 50 条
  • [1] A-eberle.de, The Mobile and Universal Power Quality Analyser PQ-Box 50
  • [2] Data centre day-ahead energy demand prediction and energy dispatch with solar PV integration
    Ajayi, Oluwafemi
    Heymann, Reolyn
    [J]. ENERGY REPORTS, 2021, 7 : 3760 - 3774
  • [3] Dynamic coupling real-time energy consumption modeling for data centers
    An, Haiyun
    Ma, Xiaoyan
    [J]. ENERGY REPORTS, 2022, 8 : 1184 - 1192
  • [4] Avelar V., 2012, White Paper #49
  • [5] Trends in Data Centre Energy Consumption under the European Code of Conduct for Data Centre Energy Efficiency
    Avgerinou, Maria
    Bertoldi, Paolo
    Castellazzi, Luca
    [J]. ENERGIES, 2017, 10 (10):
  • [6] Balodis R., 2012, IFIP Advances in Information and Communication Technology, V387
  • [7] A case study and critical assessment in calculating power usage effectiveness for a data centre
    Brady, Gemma A.
    Kapur, Nikil
    Summers, Jonathan L.
    Thompson, Harvey M.
    [J]. ENERGY CONVERSION AND MANAGEMENT, 2013, 76 : 155 - 161
  • [8] Breen T.J., 2010, P 12 IEEE INT C LAS
  • [9] Development of an independent modular air containment system for high-density data centers: Experimental investigation of row-based cooling performance and PUE
    Cho, Jinkyun
    Park, Beungyong
    Jang, Seungmin
    [J]. ENERGY, 2022, 258
  • [10] A Comparative CFD Study of Two Air Distribution Systems with Hot Aisle Containment in High-Density Data Centers
    Cho, Jinkyun
    Woo, Jesang
    Park, Beungyong
    Lim, Taesub
    [J]. ENERGIES, 2020, 13 (22)